Caledonian Sleeper
4,357 delay minutes
Most of the delay picked up by Caledonian Sleeper trains in the four weeks to 9 December 2023 came from faulty trains.
51% of these minutes were knock-on from something that happened elsewhere first. 81% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 62 | 1% | 8% | 2 a day, more than 2 of the other 4 years | - |
| Signals, points and power | 376 | 9% | 16% | 13 a day, more than 3 of the other 4 years | - |
| Weather and structures | 547 | 13% | 7% | 20 a day, more than 3 of the other 4 years | - |
| Autumn | 28 | <1% | 7% | 1 a day, more than 1 of the other 4 years | - |
| External | 13 | <1% | 4% | 0 a day, more than 2 of the other 4 years | - |
| Network management | 376 | 9% | 17% | 13 a day, more than 2 of the other 4 years | 142 |
| The operators' causes | |||||
| Train faults | 2,529 | 58% | 16% | 90 a day, the most in 5 years | 19 |
| Traincrew | 121 | 3% | 11% | 4 a day, more than 1 of the other 4 years | - |
| Stations | 48 | 1% | 3% | 2 a day, more than 1 of the other 4 years | - |
| Operations | 201 | 5% | 5% | 7 a day, the least in 5 years | 37 |
| Operator, other | 58 | 1% | 7% | 2 a day, more than 1 of the other 4 years | - |
Period by period
Whose fault, since 2018
- Their own
- 49% (97,517 minutes)
- Network Rail's
- 39% (76,837 minutes)
- Other operators' trains
- 12% (24,218 minutes)
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| ML | Wagons, coaches and parcel vehicle faults | 1,167 |
| MB | Electic Loco failure, defect, attention | 436 |
| JK | Flooding not due to exceptional weather | 300 |
| M1 | Confirmed Pantograph ADD, associated system faults, positive PANCHEX activations and train borne power switch over systems (AC) | 287 |
| MC | Diesel Loco failure, defect, attention | 278 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 211 |
| IB | Points failure (including no fault found) | 204 |
| X4 | Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions | 147 |
| OD | Delays due to National/Regional/Route Operations directives or Route Control decision or directive | 124 |
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 96 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| ML | Wagons, coaches and parcel vehicle faults | 22,255 |
| MB | Electic Loco failure, defect, attention | 18,478 |
| RD | Attaching/detaching/shunter/watering | 13,018 |
| MC | Diesel Loco failure, defect, attention | 12,366 |
| X4 | Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions | 6,345 |
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 5,788 |
| TG | Driver | 5,432 |
| I1 | Overhead line/third rail defect | 5,390 |
| MU | Depot operating problem | 4,155 |
| MD | Technical failures below the solebar | 4,109 |