Leaves on the Line

Caledonian Sleeper

CSV JSON

4,357 delay minutes

Most of the delay picked up by Caledonian Sleeper trains in the four weeks to 9 December 2023 came from faulty trains.

51% of these minutes were knock-on from something that happened elsewhere first. 81% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track621%8% 2 a day, more than 2 of the other 4 years-
Signals, points and power3769%16% 13 a day, more than 3 of the other 4 years-
Weather and structures54713%7% 20 a day, more than 3 of the other 4 years-
Autumn28<1%7% 1 a day, more than 1 of the other 4 years-
External13<1%4% 0 a day, more than 2 of the other 4 years-
Network management3769%17% 13 a day, more than 2 of the other 4 years142
The operators' causes
Train faults2,52958%16% 90 a day, the most in 5 years19
Traincrew1213%11% 4 a day, more than 1 of the other 4 years-
Stations481%3% 2 a day, more than 1 of the other 4 years-
Operations2015%5% 7 a day, the least in 5 years37
Operator, other581%7% 2 a day, more than 1 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 100 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

Whose fault, since 2018

Their own
49% (97,517 minutes)
Network Rail's
39% (76,837 minutes)
Other operators' trains
12% (24,218 minutes)

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
MLWagons, coaches and parcel vehicle faults1,167
MBElectic Loco failure, defect, attention436
JKFlooding not due to exceptional weather300
M1Confirmed Pantograph ADD, associated system faults, positive PANCHEX activations and train borne power switch over systems (AC)287
MCDiesel Loco failure, defect, attention278
MNBrake and brake systems faults; including wheel flats where no other cause had been identified211
IBPoints failure (including no fault found)204
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions147
ODDelays due to National/Regional/Route Operations directives or Route Control decision or directive124
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)96
Since 2018
CodeWhat Network Rail loggedMinutes
MLWagons, coaches and parcel vehicle faults22,255
MBElectic Loco failure, defect, attention18,478
RDAttaching/detaching/shunter/watering13,018
MCDiesel Loco failure, defect, attention12,366
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions6,345
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)5,788
TGDriver5,432
I1Overhead line/third rail defect5,390
MUDepot operating problem4,155
MDTechnical failures below the solebar4,109