Chiltern Railways
15,559 delay minutes
The biggest share (21%) of the delay picked up by Chiltern Railways trains in the four weeks to 9 December 2023 came from faulty trains.
41% of these minutes were knock-on from something that happened elsewhere first. 98% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 1,936 | 12% | 8% | 69 a day, more than 3 of the other 4 years | - |
| Signals, points and power | 1,826 | 12% | 16% | 65 a day, more than 1 of the other 4 years | 4 |
| Weather and structures | 47 | <1% | 7% | 2 a day, the least in 5 years | - |
| Autumn | 1,022 | 7% | 7% | 36 a day, more than 3 of the other 4 years | 6 |
| External | 659 | 4% | 4% | 24 a day, more than 3 of the other 4 years | 8 |
| Network management | 1,453 | 9% | 17% | 52 a day, the least in 5 years | 36 |
| The operators' causes | |||||
| Train faults | 3,261 | 21% | 16% | 116 a day, more than 1 of the other 4 years | 37 |
| Traincrew | 1,284 | 8% | 11% | 46 a day, the least in 5 years | 46 |
| Stations | 418 | 3% | 3% | 15 a day, the least in 5 years | - |
| Operations | 2,935 | 19% | 5% | 105 a day, more than 1 of the other 4 years | 63 |
| Operator, other | 720 | 5% | 7% | 26 a day, more than 1 of the other 4 years | 2 |
Period by period
Whose fault, since 2018
- Their own
- 41% (453,827 minutes)
- Network Rail's
- 49% (537,744 minutes)
- Other operators' trains
- 10% (113,469 minutes)
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TX | Delays incurred on non-Network Rail running lines or networks including London Underground (except fleet related delays) | 2,673 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 1,782 |
| TG | Driver | 981 |
| MD | Technical failures below the solebar | 964 |
| IB | Points failure (including no fault found) | 617 |
| XP | BRIDGE HIT | 612 |
| M7 | Door and Door system faults | 582 |
| QJ | Special working for leaf-fall track circuit operation | 531 |
| M8 | Technical failures above the Solebar | 444 |
| OS | Late start or delays to Railhead Conditioning or Ghost Train due to its own activity and not in reaction to another incident | 353 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TX | Delays incurred on non-Network Rail running lines or networks including London Underground (except fleet related delays) | 105,790 |
| MD | Technical failures below the solebar | 80,078 |
| TG | Driver | 72,556 |
| IC | Track circuit failure (including no fault found) | 48,701 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 45,734 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 39,855 |
| M8 | Technical failures above the Solebar | 32,746 |
| IB | Points failure (including no fault found) | 30,530 |
| MC | Diesel Loco failure, defect, attention | 27,920 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 24,674 |