72,739 delay minutes

The biggest share (19%) of the delay picked up by East Midlands Railway trains in the four weeks to 9 December 2023 came from how the network was run.

66% of these minutes were knock-on from something that happened elsewhere first. 85% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track6,6679%8% 238 a day, more than 3 of the other 4 years17
Signals, points and power11,23415%16% 401 a day, the most in 5 years39
Weather and structures4,9077%7% 175 a day, more than 3 of the other 4 years83
Autumn9,64313%7% 344 a day, the most in 5 years23
External2,7174%4% 97 a day, the most in 5 years9
Network management14,16019%17% 506 a day, more than 3 of the other 4 years339
The operators' causes
Train faults9,97014%16% 356 a day, more than 1 of the other 4 years126
Traincrew6,3449%11% 227 a day, the most in 5 years104
Stations1,8042%3% 64 a day, more than 2 of the other 4 years1
Operations1,0581%5% 38 a day, more than 1 of the other 4 years4
Operator, other4,2386%7% 151 a day, the most in 5 years14

Period by period

Delay minutes a day, period by period. Gridlines every 1,000 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

Whose fault, since 2018

Their own
25% (668,619 minutes)
Network Rail's
59% (1,587,548 minutes)
Other operators' trains
16% (417,984 minutes)

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
QJSpecial working for leaf-fall track circuit operation6,087
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.4,078
TGDriver3,951
JKFlooding not due to exceptional weather2,725
M8Technical failures above the Solebar2,591
MDTechnical failures below the solebar2,428
Q3NZ Pumps T2,302
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure1,733
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail1,719
I5Possession over-run from planned work1,710
Since 2018
CodeWhat Network Rail loggedMinutes
TGDriver152,507
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.138,253
MDTechnical failures below the solebar133,653
M8Technical failures above the Solebar119,054
ICTrack circuit failure (including no fault found)71,172
IBPoints failure (including no fault found)67,514
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)65,155
OCSignaller including mis-routing (not ERTM /ETCS related)57,213
M7Door and Door system faults56,516
IRBroken/cracked/twisted/buckled/flawed rail54,918