East Midlands Railway
72,739 delay minutes
The biggest share (19%) of the delay picked up by East Midlands Railway trains in the four weeks to 9 December 2023 came from how the network was run.
66% of these minutes were knock-on from something that happened elsewhere first. 85% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 6,667 | 9% | 8% | 238 a day, more than 3 of the other 4 years | 17 |
| Signals, points and power | 11,234 | 15% | 16% | 401 a day, the most in 5 years | 39 |
| Weather and structures | 4,907 | 7% | 7% | 175 a day, more than 3 of the other 4 years | 83 |
| Autumn | 9,643 | 13% | 7% | 344 a day, the most in 5 years | 23 |
| External | 2,717 | 4% | 4% | 97 a day, the most in 5 years | 9 |
| Network management | 14,160 | 19% | 17% | 506 a day, more than 3 of the other 4 years | 339 |
| The operators' causes | |||||
| Train faults | 9,970 | 14% | 16% | 356 a day, more than 1 of the other 4 years | 126 |
| Traincrew | 6,344 | 9% | 11% | 227 a day, the most in 5 years | 104 |
| Stations | 1,804 | 2% | 3% | 64 a day, more than 2 of the other 4 years | 1 |
| Operations | 1,058 | 1% | 5% | 38 a day, more than 1 of the other 4 years | 4 |
| Operator, other | 4,238 | 6% | 7% | 151 a day, the most in 5 years | 14 |
Period by period
Whose fault, since 2018
- Their own
- 25% (668,619 minutes)
- Network Rail's
- 59% (1,587,548 minutes)
- Other operators' trains
- 16% (417,984 minutes)
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| QJ | Special working for leaf-fall track circuit operation | 6,087 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 4,078 |
| TG | Driver | 3,951 |
| JK | Flooding not due to exceptional weather | 2,725 |
| M8 | Technical failures above the Solebar | 2,591 |
| MD | Technical failures below the solebar | 2,428 |
| Q3 | NZ Pumps T | 2,302 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 1,733 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 1,719 |
| I5 | Possession over-run from planned work | 1,710 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 152,507 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 138,253 |
| MD | Technical failures below the solebar | 133,653 |
| M8 | Technical failures above the Solebar | 119,054 |
| IC | Track circuit failure (including no fault found) | 71,172 |
| IB | Points failure (including no fault found) | 67,514 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 65,155 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 57,213 |
| M7 | Door and Door system faults | 56,516 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 54,918 |