Leaves on the Line

Elizabeth line

CSV JSON

39,806 delay minutes

The biggest share (29%) of the delay picked up by Elizabeth line trains in the four weeks to 9 December 2023 came from the operators' own operations.

70% of these minutes were knock-on from something that happened elsewhere first. 77% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track4,90912%8% 175 a day, the most in 5 years149
Signals, points and power4,06810%16% 145 a day, more than 3 of the other 4 years382
Weather and structures167<1%7% 6 a day, the most in 5 years-
Autumn8842%7% 32 a day, the most in 5 years-
External7242%4% 26 a day, the most in 5 years2
Network management4,72812%17% 169 a day, the most in 5 years630
The operators' causes
Train faults8,10820%16% 290 a day, the most in 5 years231
Traincrew1,3223%11% 47 a day, more than 3 of the other 4 years13
Stations208<1%3% 7 a day, the least in 5 years-
Operations11,65329%5% 416 a day, more than 3 of the other 4 years538
Operator, other3,0378%7% 108 a day, the most in 5 years35

Period by period

Delay minutes a day, period by period. Gridlines every 500 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

Whose fault, since 2018

Their own
43% (366,169 minutes)
Network Rail's
43% (365,908 minutes)
Other operators' trains
13% (113,142 minutes)

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
TXDelays incurred on non-Network Rail running lines or networks including London Underground (except fleet related delays)11,289
M2Delay due to ATO / ETCS equipment4,540
IRBroken/cracked/twisted/buckled/flawed rail2,573
I1Overhead line/third rail defect1,899
OUDelays not Investigated by Network Rail1,846
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.1,757
ICTrack circuit failure (including no fault found)1,395
TGDriver1,142
M0Confirmed train cab based safety system fault (including GSMR)896
Q3NZ Pumps T821
Since 2018
CodeWhat Network Rail loggedMinutes
TXDelays incurred on non-Network Rail running lines or networks including London Underground (except fleet related delays)156,625
M2Delay due to ATO / ETCS equipment55,829
IBPoints failure (including no fault found)38,877
TGDriver32,648
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.29,934
M0Confirmed train cab based safety system fault (including GSMR)28,582
M7Door and Door system faults23,902
I1Overhead line/third rail defect23,415
M8Technical failures above the Solebar20,352
J3Axle Counter Failure19,806