Leaves on the Line

Govia Thameslink Railway

CSV JSON

148,327 delay minutes

The biggest share (28%) of the delay picked up by Govia Thameslink Railway trains in the four weeks to 9 December 2023 came from how the network was run.

69% of these minutes were knock-on from something that happened elsewhere first. 95% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track15,28210%8% 546 a day, more than 3 of the other 4 years35
Signals, points and power30,84721%16% 1,102 a day, more than 2 of the other 4 years334
Weather and structures5,3284%7% 190 a day, more than 2 of the other 4 years86
Autumn3,5172%7% 126 a day, more than 1 of the other 4 years14
External6,4424%4% 230 a day, more than 3 of the other 4 years172
Network management41,07028%17% 1,467 a day, more than 1 of the other 4 years1,329
The operators' causes
Train faults11,8138%16% 422 a day, more than 1 of the other 4 years398
Traincrew19,27513%11% 688 a day, the least in 5 years925
Stations3,9893%3% 142 a day, more than 2 of the other 4 years4
Operations2,7452%5% 98 a day, the least in 5 years86
Operator, other8,0205%7% 286 a day, more than 1 of the other 4 years47

Period by period

Delay minutes a day, period by period. Gridlines every 2,000 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

Whose fault, since 2018

Their own
31% (2,902,554 minutes)
Network Rail's
63% (5,918,772 minutes)
Other operators' trains
6% (539,485 minutes)

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
TGDriver13,935
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)11,877
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.10,346
IBPoints failure (including no fault found)6,251
OCSignaller including mis-routing (not ERTM /ETCS related)6,220
IISignalling lineside cable fault5,610
IRBroken/cracked/twisted/buckled/flawed rail4,334
OKDelay caused by Operating staff oversight, issues or absence (excluding signallers and Control)4,269
TITraincrew rostering problem3,716
ICTrack circuit failure (including no fault found)3,638
Since 2018
CodeWhat Network Rail loggedMinutes
TGDriver1,046,388
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)686,400
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.517,370
OCSignaller including mis-routing (not ERTM /ETCS related)421,505
ICTrack circuit failure (including no fault found)400,568
M8Technical failures above the Solebar361,728
TITraincrew rostering problem310,278
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure260,940
OBDelayed by signaller not applying applicable regulating policy260,212
IBPoints failure (including no fault found)258,653