Govia Thameslink Railway
148,327 delay minutes
The biggest share (28%) of the delay picked up by Govia Thameslink Railway trains in the four weeks to 9 December 2023 came from how the network was run.
69% of these minutes were knock-on from something that happened elsewhere first. 95% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 15,282 | 10% | 8% | 546 a day, more than 3 of the other 4 years | 35 |
| Signals, points and power | 30,847 | 21% | 16% | 1,102 a day, more than 2 of the other 4 years | 334 |
| Weather and structures | 5,328 | 4% | 7% | 190 a day, more than 2 of the other 4 years | 86 |
| Autumn | 3,517 | 2% | 7% | 126 a day, more than 1 of the other 4 years | 14 |
| External | 6,442 | 4% | 4% | 230 a day, more than 3 of the other 4 years | 172 |
| Network management | 41,070 | 28% | 17% | 1,467 a day, more than 1 of the other 4 years | 1,329 |
| The operators' causes | |||||
| Train faults | 11,813 | 8% | 16% | 422 a day, more than 1 of the other 4 years | 398 |
| Traincrew | 19,275 | 13% | 11% | 688 a day, the least in 5 years | 925 |
| Stations | 3,989 | 3% | 3% | 142 a day, more than 2 of the other 4 years | 4 |
| Operations | 2,745 | 2% | 5% | 98 a day, the least in 5 years | 86 |
| Operator, other | 8,020 | 5% | 7% | 286 a day, more than 1 of the other 4 years | 47 |
Period by period
Whose fault, since 2018
- Their own
- 31% (2,902,554 minutes)
- Network Rail's
- 63% (5,918,772 minutes)
- Other operators' trains
- 6% (539,485 minutes)
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 13,935 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 11,877 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 10,346 |
| IB | Points failure (including no fault found) | 6,251 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 6,220 |
| II | Signalling lineside cable fault | 5,610 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 4,334 |
| OK | Delay caused by Operating staff oversight, issues or absence (excluding signallers and Control) | 4,269 |
| TI | Traincrew rostering problem | 3,716 |
| IC | Track circuit failure (including no fault found) | 3,638 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 1,046,388 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 686,400 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 517,370 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 421,505 |
| IC | Track circuit failure (including no fault found) | 400,568 |
| M8 | Technical failures above the Solebar | 361,728 |
| TI | Traincrew rostering problem | 310,278 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 260,940 |
| OB | Delayed by signaller not applying applicable regulating policy | 260,212 |
| IB | Points failure (including no fault found) | 258,653 |