6,570 delay minutes

The biggest share (28%) of the delay picked up by Grand Central trains in the four weeks to 9 December 2023 came from signal, points and power faults.

51% of these minutes were knock-on from something that happened elsewhere first. 81% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track65110%8% 23 a day, more than 1 of the other 4 years-
Signals, points and power1,85428%16% 66 a day, the most in 5 years12
Weather and structures4807%7% 17 a day, the most in 5 years-
Autumn2704%7% 10 a day, more than 2 of the other 4 years-
External5238%4% 19 a day, more than 3 of the other 4 years-
Network management89914%17% 32 a day, more than 3 of the other 4 years43
The operators' causes
Train faults1,18518%16% 42 a day, the most in 5 years24
Traincrew3185%11% 11 a day, more than 1 of the other 4 years2
Stations1622%3% 6 a day, more than 2 of the other 4 years-
Operations1062%5% 4 a day, the least in 5 years-
Operator, other1232%7% 4 a day, the least in 5 years-

Period by period

Delay minutes a day, period by period. Gridlines every 100 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

Whose fault, since 2018

Their own
18% (43,589 minutes)
Network Rail's
57% (135,577 minutes)
Other operators' trains
25% (59,349 minutes)

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
I1Overhead line/third rail defect923
M8Technical failures above the Solebar488
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.455
XRCable vandalism or theft363
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail323
QJSpecial working for leaf-fall track circuit operation239
OUDelays not Investigated by Network Rail231
TGDriver214
IDLevel crossing faults and failure incl. barrow/foot crossings and crossing treadles148
IESignalling Functional Power Supply Failure145
Since 2018
CodeWhat Network Rail loggedMinutes
MDTechnical failures below the solebar18,086
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.11,197
TGDriver10,991
IBPoints failure (including no fault found)9,734
I1Overhead line/third rail defect8,917
M8Technical failures above the Solebar8,117
MNBrake and brake systems faults; including wheel flats where no other cause had been identified7,442
ICTrack circuit failure (including no fault found)5,120
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure5,026
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail4,828