Grand Central
6,570 delay minutes
The biggest share (28%) of the delay picked up by Grand Central trains in the four weeks to 9 December 2023 came from signal, points and power faults.
51% of these minutes were knock-on from something that happened elsewhere first. 81% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 651 | 10% | 8% | 23 a day, more than 1 of the other 4 years | - |
| Signals, points and power | 1,854 | 28% | 16% | 66 a day, the most in 5 years | 12 |
| Weather and structures | 480 | 7% | 7% | 17 a day, the most in 5 years | - |
| Autumn | 270 | 4% | 7% | 10 a day, more than 2 of the other 4 years | - |
| External | 523 | 8% | 4% | 19 a day, more than 3 of the other 4 years | - |
| Network management | 899 | 14% | 17% | 32 a day, more than 3 of the other 4 years | 43 |
| The operators' causes | |||||
| Train faults | 1,185 | 18% | 16% | 42 a day, the most in 5 years | 24 |
| Traincrew | 318 | 5% | 11% | 11 a day, more than 1 of the other 4 years | 2 |
| Stations | 162 | 2% | 3% | 6 a day, more than 2 of the other 4 years | - |
| Operations | 106 | 2% | 5% | 4 a day, the least in 5 years | - |
| Operator, other | 123 | 2% | 7% | 4 a day, the least in 5 years | - |
Period by period
Whose fault, since 2018
- Their own
- 18% (43,589 minutes)
- Network Rail's
- 57% (135,577 minutes)
- Other operators' trains
- 25% (59,349 minutes)
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| I1 | Overhead line/third rail defect | 923 |
| M8 | Technical failures above the Solebar | 488 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 455 |
| XR | Cable vandalism or theft | 363 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 323 |
| QJ | Special working for leaf-fall track circuit operation | 239 |
| OU | Delays not Investigated by Network Rail | 231 |
| TG | Driver | 214 |
| ID | Level crossing faults and failure incl. barrow/foot crossings and crossing treadles | 148 |
| IE | Signalling Functional Power Supply Failure | 145 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| MD | Technical failures below the solebar | 18,086 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 11,197 |
| TG | Driver | 10,991 |
| IB | Points failure (including no fault found) | 9,734 |
| I1 | Overhead line/third rail defect | 8,917 |
| M8 | Technical failures above the Solebar | 8,117 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 7,442 |
| IC | Track circuit failure (including no fault found) | 5,120 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 5,026 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 4,828 |