Heathrow Express
9,411 delay minutes
The biggest share (29%) of the delay picked up by Heathrow Express trains in the four weeks to 9 December 2023 came from track faults.
69% of these minutes were knock-on from something that happened elsewhere first. 69% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 2,775 | 29% | 8% | 99 a day, the most in 5 years | 4 |
| Signals, points and power | 747 | 8% | 16% | 27 a day, more than 2 of the other 4 years | 90 |
| Weather and structures | 104 | 1% | 7% | 4 a day, the most in 5 years | - |
| Autumn | 38 | <1% | 7% | 1 a day, more than 3 of the other 4 years | - |
| External | 71 | <1% | 4% | 3 a day, more than 2 of the other 4 years | - |
| Network management | 1,753 | 19% | 17% | 63 a day, the most in 5 years | 35 |
| The operators' causes | |||||
| Train faults | 2,272 | 24% | 16% | 81 a day, the most in 5 years | 244 |
| Traincrew | 850 | 9% | 11% | 30 a day, the most in 5 years | 23 |
| Stations | 73 | <1% | 3% | 3 a day, more than 3 of the other 4 years | - |
| Operations | 436 | 5% | 5% | 16 a day, the most in 5 years | 5 |
| Operator, other | 292 | 3% | 7% | 10 a day, more than 2 of the other 4 years | 5 |
Period by period
Whose fault, since 2018
- Their own
- 32% (69,885 minutes)
- Network Rail's
- 47% (103,240 minutes)
- Other operators' trains
- 22% (48,411 minutes)
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IR | Broken/cracked/twisted/buckled/flawed rail | 1,451 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 1,201 |
| OU | Delays not Investigated by Network Rail | 1,169 |
| M2 | Delay due to ATO / ETCS equipment | 1,034 |
| TG | Driver | 796 |
| MT | Confirmed train borne safety system faults (not cab based) | 499 |
| TX | Delays incurred on non-Network Rail running lines or networks including London Underground (except fleet related delays) | 346 |
| IC | Track circuit failure (including no fault found) | 287 |
| I1 | Overhead line/third rail defect | 226 |
| IA | Signal failure (including no fault found) | 190 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| M2 | Delay due to ATO / ETCS equipment | 39,124 |
| TG | Driver | 12,521 |
| IC | Track circuit failure (including no fault found) | 10,912 |
| IB | Points failure (including no fault found) | 9,717 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 8,667 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 7,588 |
| I1 | Overhead line/third rail defect | 7,348 |
| M8 | Technical failures above the Solebar | 6,853 |
| J3 | Axle Counter Failure | 6,487 |
| M7 | Door and Door system faults | 6,465 |