43,772 delay minutes
The biggest share (28%) of the delay picked up by LNER trains in the four weeks to 9 December 2023 came from signal, points and power faults.
48% of these minutes were knock-on from something that happened elsewhere first. 78% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 3,324 | 8% | 8% | 119 a day, more than 1 of the other 4 years | - |
| Signals, points and power | 12,287 | 28% | 16% | 439 a day, the most in 5 years | 74 |
| Weather and structures | 7,031 | 16% | 7% | 251 a day, the most in 5 years | 62 |
| Autumn | 1,395 | 3% | 7% | 50 a day, the most in 5 years | - |
| External | 2,852 | 7% | 4% | 102 a day, more than 3 of the other 4 years | 9 |
| Network management | 6,318 | 14% | 17% | 226 a day, more than 3 of the other 4 years | 270 |
| The operators' causes | |||||
| Train faults | 5,368 | 12% | 16% | 192 a day, more than 2 of the other 4 years | 31 |
| Traincrew | 2,358 | 5% | 11% | 84 a day, more than 2 of the other 4 years | 31 |
| Stations | 562 | 1% | 3% | 20 a day, more than 1 of the other 4 years | - |
| Operations | 1,009 | 2% | 5% | 36 a day, more than 3 of the other 4 years | 2 |
| Operator, other | 1,270 | 3% | 7% | 45 a day, more than 1 of the other 4 years | - |
Period by period
Whose fault, since 2018
- Their own
- 22% (400,964 minutes)
- Network Rail's
- 62% (1,110,863 minutes)
- Other operators' trains
- 15% (274,324 minutes)
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| I1 | Overhead line/third rail defect | 8,637 |
| IV | Cutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure) | 2,637 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 2,448 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 2,302 |
| TG | Driver | 1,671 |
| I8 | Animal Strike or Incursion within the control of Network Rail | 1,594 |
| M1 | Confirmed Pantograph ADD, associated system faults, positive PANCHEX activations and train borne power switch over systems (AC) | 1,518 |
| OU | Delays not Investigated by Network Rail | 1,401 |
| XR | Cable vandalism or theft | 1,273 |
| I5 | Possession over-run from planned work | 939 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| I1 | Overhead line/third rail defect | 106,209 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 76,480 |
| IB | Points failure (including no fault found) | 69,391 |
| TG | Driver | 67,887 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 59,355 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 57,331 |
| MD | Technical failures below the solebar | 56,953 |
| MB | Electic Loco failure, defect, attention | 47,044 |
| M8 | Technical failures above the Solebar | 44,544 |
| M1 | Confirmed Pantograph ADD, associated system faults, positive PANCHEX activations and train borne power switch over systems (AC) | 43,882 |