Leaves on the Line

Lumo

CSV JSON

3,774 delay minutes

The biggest share (37%) of the delay picked up by Lumo trains in the four weeks to 9 December 2023 came from signal, points and power faults.

48% of these minutes were knock-on from something that happened elsewhere first. 74% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track39310%8% 14 a day, more than 3 of the other 4 years-
Signals, points and power1,39437%16% 50 a day, the most in 5 years2
Weather and structures82522%7% 29 a day, the most in 5 years2
Autumn722%7% 3 a day, the most in 5 years-
External1233%4% 4 a day, more than 3 of the other 4 years-
Network management39510%17% 14 a day, more than 3 of the other 4 years18
The operators' causes
Train faults2607%16% 9 a day, more than 3 of the other 4 years3
Traincrew922%11% 3 a day, more than 3 of the other 4 years-
Stations672%3% 2 a day, the most in 5 years-
Operations993%5% 4 a day, more than 3 of the other 4 years-
Operator, other551%7% 2 a day, more than 3 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 100 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

Whose fault, since 2018

Their own
13% (9,584 minutes)
Network Rail's
67% (48,633 minutes)
Other operators' trains
20% (14,282 minutes)

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
I1Overhead line/third rail defect1,086
IVCutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure)546
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.304
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions143
OUDelays not Investigated by Network Rail100
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail70
I8Animal Strike or Incursion within the control of Network Rail68
TGDriver60
I2AC/DC trip (including no fault or cause found)59
ICTrack circuit failure (including no fault found)57
Since 2018
CodeWhat Network Rail loggedMinutes
I1Overhead line/third rail defect4,022
TGDriver3,240
IBPoints failure (including no fault found)3,167
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.3,013
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail2,811
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions2,696
JDStructures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes)2,378
MUDepot operating problem2,131
MDTechnical failures below the solebar1,965
M1Confirmed Pantograph ADD, associated system faults, positive PANCHEX activations and train borne power switch over systems (AC)1,919