TransPennine Express
70,349 delay minutes
The biggest share (17%) of the delay picked up by TransPennine Express trains in the four weeks to 9 December 2023 came from faulty trains.
71% of these minutes were knock-on from something that happened elsewhere first. 91% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 6,607 | 9% | 8% | 236 a day, more than 3 of the other 4 years | 47 |
| Signals, points and power | 7,418 | 11% | 16% | 265 a day, more than 2 of the other 4 years | 16 |
| Weather and structures | 6,289 | 9% | 7% | 225 a day, the most in 5 years | 48 |
| Autumn | 5,817 | 8% | 7% | 208 a day, the most in 5 years | 4 |
| External | 2,576 | 4% | 4% | 92 a day, the most in 5 years | 10 |
| Network management | 10,513 | 15% | 17% | 375 a day, more than 3 of the other 4 years | 807 |
| The operators' causes | |||||
| Train faults | 12,228 | 17% | 16% | 437 a day, more than 2 of the other 4 years | 151 |
| Traincrew | 10,697 | 15% | 11% | 382 a day, more than 3 of the other 4 years | 138 |
| Stations | 2,069 | 3% | 3% | 74 a day, more than 2 of the other 4 years | - |
| Operations | 2,899 | 4% | 5% | 104 a day, more than 3 of the other 4 years | 23 |
| Operator, other | 3,238 | 5% | 7% | 116 a day, more than 2 of the other 4 years | 12 |
Period by period
Whose fault, since 2018
- Their own
- 24% (627,187 minutes)
- Network Rail's
- 50% (1,315,950 minutes)
- Other operators' trains
- 26% (675,197 minutes)
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 6,127 |
| OU | Delays not Investigated by Network Rail | 3,595 |
| TH | (Senior) Conductor/Train Manager | 3,551 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 3,435 |
| QJ | Special working for leaf-fall track circuit operation | 3,054 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 2,957 |
| MD | Technical failures below the solebar | 2,321 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 2,087 |
| Q3 | NZ Pumps T | 1,861 |
| M8 | Technical failures above the Solebar | 1,793 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 265,858 |
| MD | Technical failures below the solebar | 125,668 |
| M8 | Technical failures above the Solebar | 90,996 |
| TH | (Senior) Conductor/Train Manager | 88,035 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 76,577 |
| IB | Points failure (including no fault found) | 70,892 |
| M7 | Door and Door system faults | 67,365 |
| IC | Track circuit failure (including no fault found) | 64,656 |
| MU | Depot operating problem | 61,684 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 61,218 |