98,524 delay minutes

The biggest share (21%) of the delay picked up on the East Coast route in the four weeks to 9 December 2023 came from signal, points and power faults.

57% of these minutes were knock-on from something that happened elsewhere first. 85% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track7,1257%8% 254 a day, more than 1 of the other 4 years14
Signals, points and power21,06021%16% 752 a day, the most in 5 years104
Weather and structures10,83911%7% 387 a day, the most in 5 years83
Autumn4,2664%7% 152 a day, more than 3 of the other 4 years6
External4,8335%4% 173 a day, more than 3 of the other 4 years34
Network management18,38619%17% 657 a day, more than 3 of the other 4 years937
The operators' causes
Train faults12,20512%16% 436 a day, more than 2 of the other 4 years210
Traincrew10,52211%11% 376 a day, more than 3 of the other 4 years524
Stations2,2332%3% 80 a day, more than 2 of the other 4 years3
Operations3,3393%5% 119 a day, the most in 5 years16
Operator, other3,7184%7% 133 a day, more than 1 of the other 4 years19

Period by period

Delay minutes a day, period by period. Gridlines every 1,000 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

Worst stretches since 2018

Where the incidents started, by cause, counting all the knock-on delay they caused anywhere.

Track
Durham to Ferryhill Sth. Jn.24,023
King Edward Bridge South Jn to Durham19,037
Darlington to Northallerton14,043
Potters Bar to Welwyn Garden City13,867
Peterborough to Huntingdon13,582
Grantham to Newark North Gate12,745
Doncaster11,609
Colton Jn to Church Fenton11,586
Alexandra Palace to Potters Bar11,448
Newark North Gate to Grantham11,298
Signals, points and power
Peterborough39,137
Grantham to Newark North Gate34,625
Alexandra Palace to Potters Bar31,107
Doncaster26,341
Retford to Newark North Gate21,298
Retford19,201
Darlington19,013
Sandy to Huntingdon18,880
Huntingdon to Sandy17,802
Hitchin16,595
Weather and structures
Heaton Sth. Jn. to Morpeth34,187
York23,343
Ferryhill Sth. Jn. to Darlington19,015
Sandy to Hitchin15,224
Huntingdon to Holme Jn.12,912
Newark North Gate to Grantham11,087
Belford L.C. to Berwick-upon-Tweed10,794
Alexandra Palace to Potters Bar10,540
Durham to King Edward Bridge South Jn9,630
Doncaster to Thorne Jn9,549
Autumn
Potters Bar to Welwyn Garden City2,300
Welwyn Garden City to Woolmer Green Jn.1,985
Royston to Letchworth Garden City1,910
York to Malton1,436
Peterborough to Tallington Jn.1,243
Welwyn Garden City to Potters Bar909
York877
Tallington Jn.840
Hertford North to Gordon Hill825
Alexandra Palace to Potters Bar733
External
Loversall Carr Jn to Retford12,076
Retford to Loversall Carr Jn8,855
Stevenage8,381
Alexandra Palace7,783
Potters Bar to Alexandra Palace7,709
Huntingdon to Holme Jn.7,549
Newark North Gate7,131
Durham to Ferryhill Sth. Jn.6,384
Peterborough6,273
Newark North Gate to Retford5,503
Network management
York53,809
London Kings Cross53,609
Doncaster24,694
Colton Jn to York15,864
Peterborough13,808
Newcastle13,750
Finsbury Park11,931
Holme Jn. to Peterborough11,743
Finsbury Park to Alexandra Palace11,238
Retford to Newark North Gate11,124
Train faults
York88,365
London Kings Cross60,283
Newcastle54,625
Doncaster48,229
Heaton T&R.S.M.D.34,279
Darlington26,980
Peterborough23,289
Darlington to Northallerton21,337
Hitchin to Sandy21,040
Grantham20,853
Traincrew
York99,372
London Kings Cross65,048
Newcastle59,108
Finsbury Park56,121
Peterborough50,853
Welwyn Garden City29,713
Doncaster25,311
Stevenage15,958
Heaton T&R.S.M.D.15,374
Hornsey E.M.U.D.14,233
Stations
York28,609
Newcastle12,706
London Kings Cross10,636
Durham10,308
Doncaster7,624
Darlington6,009
Grantham4,606
Peterborough4,503
Berwick-upon-Tweed3,871
Stevenage2,848
Operations
York16,540
London Kings Cross10,602
Newcastle9,922
Doncaster9,557
Finsbury Park7,336
Pelaw Metro Junction6,314
Peterborough4,316
Royston to Letchworth Garden City4,098
Pelaw Jn.2,903
Darlington2,844
Operator, other
York9,625
Doncaster7,319
Doncaster Up Decoy6,847
Stevenage6,421
London Kings Cross6,203
Peterborough5,959
Darlington4,706
Newcastle4,247
Peterborough North Yd Gbrf3,885
Finsbury Park3,559

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
I1Overhead line/third rail defect12,253
TGDriver6,858
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.5,138
OUDelays not Investigated by Network Rail4,839
IVCutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure)4,521
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail3,776
QJSpecial working for leaf-fall track circuit operation2,514
XRCable vandalism or theft2,289
I8Animal Strike or Incursion within the control of Network Rail2,281
M8Technical failures above the Solebar1,977
Since 2018
CodeWhat Network Rail loggedMinutes
TGDriver385,613
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.215,308
I1Overhead line/third rail defect187,260
IBPoints failure (including no fault found)160,684
MDTechnical failures below the solebar152,285
M8Technical failures above the Solebar148,522
MNBrake and brake systems faults; including wheel flats where no other cause had been identified110,036
ICTrack circuit failure (including no fault found)108,998
TITraincrew rostering problem104,753
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure102,349