Leaves on the Line

Sussex route

CSV JSON

87,204 delay minutes

The biggest share (28%) of the delay picked up on the Sussex route in the four weeks to 9 December 2023 came from how the network was run.

68% of these minutes were knock-on from something that happened elsewhere first. 96% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track11,72313%8% 419 a day, more than 3 of the other 4 years29
Signals, points and power17,22220%16% 615 a day, more than 2 of the other 4 years185
Weather and structures3,9365%7% 141 a day, more than 3 of the other 4 years60
Autumn1,1531%7% 41 a day, the least in 5 years7
External4,7125%4% 168 a day, more than 3 of the other 4 years122
Network management24,57128%17% 878 a day, more than 1 of the other 4 years574
The operators' causes
Train faults6,6428%16% 237 a day, more than 1 of the other 4 years283
Traincrew8,56310%11% 306 a day, the least in 5 years230
Stations3,0814%3% 110 a day, more than 2 of the other 4 years12
Operations2,0402%5% 73 a day, more than 2 of the other 4 years54
Operator, other3,5624%7% 127 a day, more than 1 of the other 4 years25

Period by period

Delay minutes a day, period by period. Gridlines every 1,000 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

Worst stretches since 2018

Where the incidents started, by cause, counting all the knock-on delay they caused anywhere.

Track
Gatwick Airport to Earlswood (Surrey)28,360
Earlswood (Surrey) to Gatwick Airport25,442
Norwood Junction to New Cross Gate19,377
Earlswood (Surrey) to Stoats Nest Jn.17,027
Keymer Jn to Preston Park13,447
London Victoria12,431
Balham11,670
Battersea Park to Clapham Junction11,204
Polegate to Lewes11,069
Stoats Nest Jn.10,514
Signals, points and power
Three Bridges37,796
Norwood Junction to New Cross Gate33,421
Redhill31,458
Stoats Nest Jn. to Earlswood (Surrey)29,581
Earlswood (Surrey)25,154
Gatwick Airport24,425
London Victoria22,543
Gatwick Airport to Earlswood (Surrey)22,433
Selhurst to Balham22,315
Brighton19,434
Weather and structures
Earlswood (Surrey) to Gatwick Airport55,194
Three Bridges26,224
Balcombe Tunnel Jn to Haywards Heath16,804
Keymer Jn to Haywards Heath10,772
Balcombe Tunnel Jn10,663
London Victoria8,624
Stoats Nest Jn.7,944
Mitcham Junction6,534
Horsham to Dorking6,403
Haywards Heath to Keymer Jn6,004
Autumn
Chichester to Havant3,614
Balham to Selhurst1,755
East Croydon to Purley1,253
Reigate to Shalford (Surrey)834
Purley to East Croydon710
Hurst Green to Crowborough696
Crowborough to Hurst Green589
Earlswood (Surrey) to Gatwick Airport585
Tattenham Corner to Coulsdon Town564
Gatwick Airport to Earlswood (Surrey)560
External
Three Bridges22,338
Stoats Nest Jn. to Earlswood (Surrey)14,894
Tulse Hill10,708
London Victoria9,987
East Croydon to Norwood Junction9,962
Horsham to Pulborough7,159
Battersea Park to Clapham Junction6,310
East Croydon to Purley5,989
Pulborough to Horsham5,988
Balham to Selhurst5,430
Network management
London Victoria69,072
Gatwick Airport64,599
East Croydon64,299
Three Bridges59,787
Earlswood (Surrey) to Gatwick Airport50,203
Selhurst to East Croydon46,084
Balham to Selhurst41,530
Norwood Junction to East Croydon39,196
East Croydon to Purley38,200
Purley to East Croydon33,886
Train faults
London Victoria61,755
Three Bridges26,467
East Croydon24,151
Gatwick Airport22,257
Selhurst T&R.S.M.D19,951
Brighton18,829
Horsham17,477
Purley14,157
Redhill12,483
Haywards Heath9,535
Traincrew
London Victoria102,490
Brighton57,092
Three Bridges56,934
Horsham50,588
Barnham29,997
East Croydon27,584
Purley24,806
Gatwick Airport24,598
Eastbourne18,367
Haywards Heath17,261
Stations
London Victoria20,019
East Croydon15,469
Gatwick Airport9,259
Three Bridges7,845
Norwood Junction to New Cross Gate6,557
Redhill5,497
Brighton5,070
Purley4,932
Haywards Heath3,497
Norwood Junction3,212
Operations
London Victoria25,162
Three Bridges12,691
Brighton8,109
East Croydon5,827
Haywards Heath5,379
Redhill4,858
Gatwick Airport4,837
Crawley to Horsham4,552
Purley4,082
Horsham4,069
Operator, other
London Victoria13,025
Gatwick Airport9,395
East Croydon8,860
Balham to Selhurst8,534
Balham6,525
Chichester to Havant4,617
East Croydon to Purley4,519
Tulse Hill3,816
Preston Park to Keymer Jn3,616
Three Bridges3,347

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)8,457
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.7,842
TGDriver6,047
OCSignaller including mis-routing (not ERTM /ETCS related)4,423
IBPoints failure (including no fault found)4,415
IRBroken/cracked/twisted/buckled/flawed rail3,672
IISignalling lineside cable fault3,375
IVCutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure)2,663
OBDelayed by signaller not applying applicable regulating policy2,319
XBVandalism or theft (including the placing of objects on the line)2,161
Since 2018
CodeWhat Network Rail loggedMinutes
TGDriver531,715
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)504,490
OCSignaller including mis-routing (not ERTM /ETCS related)317,768
ICTrack circuit failure (including no fault found)259,483
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.257,671
OBDelayed by signaller not applying applicable regulating policy218,183
M8Technical failures above the Solebar162,768
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure161,802
IBPoints failure (including no fault found)149,190
IRBroken/cracked/twisted/buckled/flawed rail147,873