Ashburys
1,707 delay minutes
The biggest share (24%) of the delay picked up at Ashburys in the four weeks to 9 December 2023 came from faulty trains.
67% of these minutes were knock-on from something that happened elsewhere first. 82% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 107 | 6% | 8% | 4 a day, more than 2 of the other 4 years | - |
| Signals, points and power | 92 | 5% | 16% | 3 a day, more than 2 of the other 4 years | - |
| Weather and structures | 38 | 2% | 7% | 1 a day, more than 2 of the other 4 years | - |
| Autumn | 231 | 14% | 7% | 8 a day, more than 3 of the other 4 years | - |
| External | 23 | 1% | 4% | 1 a day, more than 1 of the other 4 years | - |
| Network management | 300 | 18% | 17% | 11 a day, more than 2 of the other 4 years | 1 |
| The operators' causes | |||||
| Train faults | 405 | 24% | 16% | 14 a day, more than 2 of the other 4 years | - |
| Traincrew | 171 | 10% | 11% | 6 a day, more than 2 of the other 4 years | - |
| Stations | 55 | 3% | 3% | 2 a day, more than 2 of the other 4 years | - |
| Operations | 78 | 5% | 5% | 3 a day, more than 2 of the other 4 years | - |
| Operator, other | 208 | 12% | 7% | 7 a day, more than 2 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| MD | Technical failures below the solebar | 205 |
| Q3 | NZ Pumps T | 154 |
| TT | Leaf fall Neutral | 152 |
| OU | Delays not Investigated by Network Rail | 118 |
| TG | Driver | 114 |
| TH | (Senior) Conductor/Train Manager | 57 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 53 |
| M8 | Technical failures above the Solebar | 51 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 49 |
| JP | Failure to maintain vegetation within network boundaries in accordance with prevailing Network Rail standards | 49 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 6,063 |
| MD | Technical failures below the solebar | 4,321 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 3,962 |
| IC | Track circuit failure (including no fault found) | 2,717 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 2,388 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 2,257 |
| M8 | Technical failures above the Solebar | 2,124 |
| TH | (Senior) Conductor/Train Manager | 2,071 |
| MU | Depot operating problem | 2,003 |
| M7 | Door and Door system faults | 1,956 |