678 delay minutes
The biggest share (30%) of the delay picked up at Ascot in the four weeks to 9 December 2023 came from signal, points and power faults.
56% of these minutes were knock-on from something that happened elsewhere first. 94% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 16 | 2% | 8% | 1 a day, more than 1 of the other 4 years | 9 |
| Signals, points and power | 201 | 30% | 16% | 7 a day, more than 3 of the other 4 years | 10 |
| Weather and structures | 37 | 5% | 7% | 1 a day, more than 3 of the other 4 years | 5 |
| Autumn | 89 | 13% | 7% | 3 a day, more than 3 of the other 4 years | - |
| External | 24 | 4% | 4% | 1 a day, more than 2 of the other 4 years | - |
| Network management | 116 | 17% | 17% | 4 a day, the least in 5 years | 1 |
| The operators' causes | |||||
| Train faults | 42 | 6% | 16% | 2 a day, the least in 5 years | 3 |
| Traincrew | 18 | 3% | 11% | 1 a day, the least in 5 years | 21 |
| Stations | 35 | 5% | 3% | 1 a day, more than 1 of the other 4 years | - |
| Operations | - | - | 5% | 0 a day, the least in 5 years | 5 |
| Operator, other | 100 | 15% | 7% | 4 a day, more than 2 of the other 4 years | 1 |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IB | Points failure (including no fault found) | 91 |
| Q3 | NZ Pumps T | 79 |
| TT | Leaf fall Neutral | 79 |
| IC | Track circuit failure (including no fault found) | 52 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 51 |
| IE | Signalling Functional Power Supply Failure | 35 |
| T2 | Delay at unstaffed station to non-DOO train | 32 |
| OK | Delay caused by Operating staff oversight, issues or absence (excluding signallers and Control) | 29 |
| IV | Cutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure) | 19 |
| I6 | Delays as a result of line blocks / track patrols (including late handback) | 18 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 3,721 |
| IC | Track circuit failure (including no fault found) | 3,002 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 1,896 |
| IB | Points failure (including no fault found) | 1,770 |
| TG | Driver | 1,686 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 1,604 |
| XO | External trees, building or structures encroaching or falling onto network infrastructure (not weather or vandalism) | 1,488 |
| JX | Miscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains) | 1,257 |
| TI | Traincrew rostering problem | 1,081 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 999 |