Leaves on the Line

Ash Vale

AHV Wessex route
CSV JSON

1,589 delay minutes

The biggest share (36%) of the delay picked up at Ash Vale in the four weeks to 9 December 2023 came from signal, points and power faults.

43% of these minutes were knock-on from something that happened elsewhere first. 92% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track996%8% 4 a day, more than 2 of the other 4 years-
Signals, points and power57536%16% 21 a day, the most in 5 years-
Weather and structures19112%7% 7 a day, the most in 5 years-
Autumn18111%7% 6 a day, more than 3 of the other 4 years-
External362%4% 1 a day, more than 2 of the other 4 years-
Network management1308%17% 5 a day, more than 1 of the other 4 years-
The operators' causes
Train faults684%16% 2 a day, more than 3 of the other 4 years-
Traincrew745%11% 3 a day, the most in 5 years-
Stations181%3% 1 a day, more than 1 of the other 4 years-
Operations272%5% 1 a day, the most in 5 years-
Operator, other19012%7% 7 a day, more than 2 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 20 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
IBPoints failure (including no fault found)465
JDStructures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes)183
Q3NZ Pumps T140
TTLeaf fall Neutral140
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.67
IESignalling Functional Power Supply Failure57
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)38
TGDriver34
OCSignaller including mis-routing (not ERTM /ETCS related)32
VZOther passenger or external causes the responsibility of TOC29
Since 2018
CodeWhat Network Rail loggedMinutes
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.3,380
IRBroken/cracked/twisted/buckled/flawed rail2,561
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)2,512
IBPoints failure (including no fault found)2,351
ICTrack circuit failure (including no fault found)1,959
TGDriver1,132
TTLeaf fall Neutral1,090
OCSignaller including mis-routing (not ERTM /ETCS related)1,089
MDTechnical failures below the solebar832
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure812