Leaves on the Line

Alderley Edge

ALD North West route
CSV JSON

1,072 delay minutes

The biggest share (19%) of the delay picked up at Alderley Edge in the four weeks to 9 December 2023 came from how the network was run.

63% of these minutes were knock-on from something that happened elsewhere first. 78% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track797%8% 3 a day, the most in 5 years-
Signals, points and power12812%16% 5 a day, more than 2 of the other 4 years-
Weather and structures12912%7% 5 a day, the most in 5 years-
Autumn10310%7% 4 a day, the most in 5 years-
External141%4% 1 a day, more than 2 of the other 4 years-
Network management20619%17% 7 a day, the most in 5 years26
The operators' causes
Train faults12812%16% 5 a day, the least in 5 years5
Traincrew737%11% 3 a day, more than 3 of the other 4 years4
Stations323%3% 1 a day, more than 2 of the other 4 years-
Operations222%5% 1 a day, the least in 5 years3
Operator, other15815%7% 6 a day, the most in 5 years-

Period by period

Delay minutes a day, period by period. Gridlines every 20 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail113
Q3NZ Pumps T87
TTLeaf fall Neutral87
ODDelays due to National/Regional/Route Operations directives or Route Control decision or directive66
OUDelays not Investigated by Network Rail65
MPRail / wheel interface, adhesion problems (including ice on the running rail)64
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.59
IBPoints failure (including no fault found)48
TGDriver48
ICTrack circuit failure (including no fault found)44
Since 2018
CodeWhat Network Rail loggedMinutes
MSPlanned underpowered or shortformed service and or vehicle, incl. exam set swaps2,364
MDTechnical failures below the solebar2,329
TGDriver1,940
ICTrack circuit failure (including no fault found)1,769
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure1,666
IBPoints failure (including no fault found)1,643
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)1,258
I1Overhead line/third rail defect1,041
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure1,005
M8Technical failures above the Solebar987