Leaves on the Line

Alfreton

ALF East Midlands route
CSV JSON

27 delay minutes

Most of the delay picked up at Alfreton in the four weeks to 9 December 2023 came from how the network was run.

100% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%1
Signals, points and power--16%-
Weather and structures--7%-
Autumn--7%-
External--4%-
Network management27100%17%-
The operators' causes
Train faults--16%-
Traincrew--11%-
Stations--3%-
Operations--5%-
Operator, other--7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 1 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
I5Possession over-run from planned work22
OARegulation Decision Made With Best Endeavours5
Since 2018
CodeWhat Network Rail loggedMinutes
I5Possession over-run from planned work22
IESignalling Functional Power Supply Failure18
IASignal failure (including no fault found)16
XLFire external to but directly affecting the network (incl. line blocks for emergency services attending off network incidents)14
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure6
OARegulation Decision Made With Best Endeavours5
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)3
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)3
IVCutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure)3