Altrincham
570 delay minutes
Most of the delay picked up at Altrincham in the four weeks to 9 December 2023 came from weather and structures.
15% of these minutes were knock-on from something that happened elsewhere first. 97% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | - | - | 8% | 0 a day, the least in 5 years | - |
| Signals, points and power | 58 | 10% | 16% | 2 a day, more than 3 of the other 4 years | - |
| Weather and structures | 304 | 53% | 7% | 11 a day, the most in 5 years | - |
| Autumn | 3 | <1% | 7% | 0 a day, the least in 5 years | - |
| External | 12 | 2% | 4% | 0 a day, more than 3 of the other 4 years | - |
| Network management | 58 | 10% | 17% | 2 a day, more than 2 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 87 | 15% | 16% | 3 a day, more than 3 of the other 4 years | 2 |
| Traincrew | 12 | 2% | 11% | 0 a day, more than 1 of the other 4 years | - |
| Stations | 8 | 1% | 3% | 0 a day, more than 1 of the other 4 years | - |
| Operations | 17 | 3% | 5% | 1 a day, more than 2 of the other 4 years | - |
| Operator, other | 11 | 2% | 7% | 0 a day, the least in 5 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| JK | Flooding not due to exceptional weather | 271 |
| MC | Diesel Loco failure, defect, attention | 64 |
| OU | Delays not Investigated by Network Rail | 52 |
| IB | Points failure (including no fault found) | 39 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 30 |
| XN | Road or crossing related incidents inc. cars on line, crossing misuse and priority to emergency services (NOT bridge strikes) | 12 |
| TZ | Other Passenger Train Operating Company causes | 11 |
| IA | Signal failure (including no fault found) | 10 |
| MU | Depot operating problem | 9 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 8 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 1,854 |
| JS | Condition of Track TSR outside the Timetable Planning Rules | 1,372 |
| IC | Track circuit failure (including no fault found) | 708 |
| TG | Driver | 598 |
| JK | Flooding not due to exceptional weather | 582 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 553 |
| JB | Reactionary Delay to 'P' coded TSRs | 518 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 478 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 438 |
| TZ | Other Passenger Train Operating Company causes | 429 |