Leaves on the Line

Appleby

APP North West route
CSV JSON

67 delay minutes

Most of the delay picked up at Appleby in the four weeks to 9 December 2023 came from weather and structures.

100% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power--16%-
Weather and structures67100%7%1
Autumn--7%-
External--4%-
Network management--17%-
The operators' causes
Train faults--16%-
Traincrew--11%-
Stations--3%-
Operations--5%-
Operator, other--7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure67
Since 2018
CodeWhat Network Rail loggedMinutes
TGDriver194
MDTechnical failures below the solebar136
QMTrain schedule/STP Process including erroneous simplifiers132
RMWaiting connections from other transport modes120
Q3NZ Pumps T114
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure91
JKFlooding not due to exceptional weather91
OEFailure to lay Sandite or operate Railhead Conditioning train as programmed89
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)87
T3Waiting connections from other transport modes83