195 delay minutes
Most of the delay picked up at Aylesbury Vale Parkway in the four weeks to 9 December 2023 came from the operators' own operations.
91% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | Trains cancelled |
|---|---|---|---|---|
| Network Rail's causes | ||||
| Track | - | - | 8% | - |
| Signals, points and power | 12 | 6% | 16% | - |
| Weather and structures | - | - | 7% | - |
| Autumn | 14 | 7% | 7% | 1 |
| External | - | - | 4% | - |
| Network management | 11 | 6% | 17% | - |
| The operators' causes | ||||
| Train faults | 23 | 12% | 16% | 1 |
| Traincrew | 5 | 3% | 11% | - |
| Stations | 5 | 3% | 3% | - |
| Operations | 119 | 61% | 5% | - |
| Operator, other | 6 | 3% | 7% | - |
Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TX | Delays incurred on non-Network Rail running lines or networks including London Underground (except fleet related delays) | 114 |
| MD | Technical failures below the solebar | 9 |
| MU | Depot operating problem | 9 |
| OS | Late start or delays to Railhead Conditioning or Ghost Train due to its own activity and not in reaction to another incident | 9 |
| J0 | Telecom equipment radio failure (GSM-R) | 7 |
| QJ | Special working for leaf-fall track circuit operation | 6 |
| VX | External events occurring on the LUL or other non NR running lines | 6 |
| IL | Token equipment failure (including no fault found) | 5 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 5 |
| OE | Failure to lay Sandite or operate Railhead Conditioning train as programmed | 5 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TX | Delays incurred on non-Network Rail running lines or networks including London Underground (except fleet related delays) | 1,153 |
| JS | Condition of Track TSR outside the Timetable Planning Rules | 935 |
| MD | Technical failures below the solebar | 545 |
| IC | Track circuit failure (including no fault found) | 396 |
| TG | Driver | 388 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 270 |
| MT | Confirmed train borne safety system faults (not cab based) | 222 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 181 |
| M8 | Technical failures above the Solebar | 178 |
| M7 | Door and Door system faults | 159 |