Burscough Bridge
640 delay minutes
The biggest share (19%) of the delay picked up at Burscough Bridge in the four weeks to 9 December 2023 came from autumn leaves.
36% of these minutes were knock-on from something that happened elsewhere first. 95% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 5 | <1% | 8% | 0 a day, more than 3 of the other 4 years | - |
| Signals, points and power | 8 | 1% | 16% | 0 a day, the least in 5 years | - |
| Weather and structures | 7 | 1% | 7% | 0 a day, more than 2 of the other 4 years | - |
| Autumn | 122 | 19% | 7% | 4 a day, more than 2 of the other 4 years | - |
| External | 48 | 8% | 4% | 2 a day, more than 3 of the other 4 years | - |
| Network management | 85 | 13% | 17% | 3 a day, the most in 5 years | - |
| The operators' causes | |||||
| Train faults | 91 | 14% | 16% | 3 a day, more than 1 of the other 4 years | - |
| Traincrew | 64 | 10% | 11% | 2 a day, the most in 5 years | - |
| Stations | 15 | 2% | 3% | 1 a day, more than 1 of the other 4 years | - |
| Operations | 85 | 13% | 5% | 3 a day, more than 2 of the other 4 years | - |
| Operator, other | 111 | 17% | 7% | 4 a day, more than 2 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| Q3 | NZ Pumps T | 111 |
| TT | Leaf fall Neutral | 109 |
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 55 |
| XN | Road or crossing related incidents inc. cars on line, crossing misuse and priority to emergency services (NOT bridge strikes) | 48 |
| MD | Technical failures below the solebar | 45 |
| TG | Driver | 45 |
| M7 | Door and Door system faults | 31 |
| OU | Delays not Investigated by Network Rail | 25 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 23 |
| TZ | Other Passenger Train Operating Company causes | 20 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 3,569 |
| MD | Technical failures below the solebar | 2,753 |
| TG | Driver | 2,563 |
| Q3 | NZ Pumps T | 1,093 |
| RB | Passengers joining/alighting | 887 |
| TT | Leaf fall Neutral | 749 |
| TH | (Senior) Conductor/Train Manager | 685 |
| M7 | Door and Door system faults | 675 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 669 |
| RC | re-booked assistance for a person with reduced mobility joining/alighting, | 650 |