15 delay minutes

Most of the delay picked up at Beccles in the four weeks to 9 December 2023 came from outside causes like vandalism, cable theft, animals and fires.

53% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power--16%-
Weather and structures--7%-
Autumn--7%-
External853%4%1
Network management747%17%2
The operators' causes
Train faults--16%-
Traincrew--11%-
Stations--3%-
Operations--5%-
Operator, other--7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 5 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
XNRoad or crossing related incidents inc. cars on line, crossing misuse and priority to emergency services (NOT bridge strikes)8
JPFailure to maintain vegetation within network boundaries in accordance with prevailing Network Rail standards7
Since 2018
CodeWhat Network Rail loggedMinutes
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail83
JDStructures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes)61
I7Engineer's train late into, from or failed in possession42
J3Axle Counter Failure34
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure31
ICTrack circuit failure (including no fault found)30
MUDepot operating problem21
M8Technical failures above the Solebar21
MDTechnical failures below the solebar19
M7Door and Door system faults17