Bracknell
358 delay minutes
The biggest share (20%) of the delay picked up at Bracknell in the four weeks to 9 December 2023 came from signal, points and power faults.
67% of these minutes were knock-on from something that happened elsewhere first. 99% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 7 | 2% | 8% | 0 a day, more than 1 of the other 4 years | - |
| Signals, points and power | 72 | 20% | 16% | 3 a day, more than 3 of the other 4 years | - |
| Weather and structures | - | - | 7% | 0 a day, the least in 5 years | - |
| Autumn | 36 | 10% | 7% | 1 a day, more than 2 of the other 4 years | - |
| External | 11 | 3% | 4% | 0 a day, more than 3 of the other 4 years | - |
| Network management | 49 | 14% | 17% | 2 a day, more than 1 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 43 | 12% | 16% | 2 a day, the most in 5 years | 1 |
| Traincrew | 30 | 8% | 11% | 1 a day, more than 2 of the other 4 years | 1 |
| Stations | 36 | 10% | 3% | 1 a day, more than 3 of the other 4 years | - |
| Operations | 33 | 9% | 5% | 1 a day, the most in 5 years | - |
| Operator, other | 41 | 11% | 7% | 1 a day, more than 3 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| I4 | OHLE/third rail power supply failure or reduction | 72 |
| Q3 | NZ Pumps T | 33 |
| TT | Leaf fall Neutral | 33 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 32 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 22 |
| TG | Driver | 16 |
| TA | Train-crew/loco/stock/unit diagram issues | 15 |
| FO | Time Lost en-route believed to be operator cause and information required from Operator (Ops Responsibility) | 12 |
| M7 | Door and Door system faults | 10 |
| RQ | Un-booked assistance for a person with reduced mobility joining/alighting, | 9 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| OT | Ops Safety TSR implemented for sighting issues relating to foot crossings, level crossings or signals (Not vegetation caused) | 2,127 |
| IC | Track circuit failure (including no fault found) | 1,253 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 954 |
| TG | Driver | 889 |
| ID | Level crossing faults and failure incl. barrow/foot crossings and crossing treadles | 729 |
| VH | Passenger Communication cord, door egress or emergency train alarm operated | 607 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 586 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 571 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 570 |
| IB | Points failure (including no fault found) | 423 |