Bradford Interchange

BDI North & East route
CSV JSON

6,290 delay minutes

The biggest share (18%) of the delay picked up at Bradford Interchange in the four weeks to 9 December 2023 came from how the network was run.

53% of these minutes were knock-on from something that happened elsewhere first. 80% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track2364%8% 8 a day, more than 3 of the other 4 years8
Signals, points and power1,09817%16% 39 a day, the most in 5 years8
Weather and structures5218%7% 19 a day, the most in 5 years5
Autumn67011%7% 24 a day, more than 3 of the other 4 years3
External4347%4% 16 a day, the most in 5 years3
Network management1,11118%17% 40 a day, the most in 5 years24
The operators' causes
Train faults85114%16% 30 a day, more than 3 of the other 4 years20
Traincrew5649%11% 20 a day, the most in 5 years40
Stations1232%3% 4 a day, the most in 5 years1
Operations2754%5% 10 a day, the most in 5 years3
Operator, other4076%7% 15 a day, more than 3 of the other 4 years1

Period by period

Delay minutes a day, period by period. Gridlines every 100 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
IHPower Supply And Distribution System Failure759
JXMiscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains)479
OUDelays not Investigated by Network Rail413
TGDriver399
Q3NZ Pumps T367
XOExternal trees, building or structures encroaching or falling onto network infrastructure (not weather or vandalism)355
TTLeaf fall Neutral348
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail330
M7Door and Door system faults273
QJSpecial working for leaf-fall track circuit operation235
Since 2018
CodeWhat Network Rail loggedMinutes
MDTechnical failures below the solebar10,160
TGDriver10,022
MSPlanned underpowered or shortformed service and or vehicle, incl. exam set swaps5,075
M7Door and Door system faults4,882
MNBrake and brake systems faults; including wheel flats where no other cause had been identified4,400
M8Technical failures above the Solebar4,190
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.4,113
IVCutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure)4,010
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)3,781
Q3NZ Pumps T3,676