Bradford Interchange
6,290 delay minutes
The biggest share (18%) of the delay picked up at Bradford Interchange in the four weeks to 9 December 2023 came from how the network was run.
53% of these minutes were knock-on from something that happened elsewhere first. 80% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 236 | 4% | 8% | 8 a day, more than 3 of the other 4 years | 8 |
| Signals, points and power | 1,098 | 17% | 16% | 39 a day, the most in 5 years | 8 |
| Weather and structures | 521 | 8% | 7% | 19 a day, the most in 5 years | 5 |
| Autumn | 670 | 11% | 7% | 24 a day, more than 3 of the other 4 years | 3 |
| External | 434 | 7% | 4% | 16 a day, the most in 5 years | 3 |
| Network management | 1,111 | 18% | 17% | 40 a day, the most in 5 years | 24 |
| The operators' causes | |||||
| Train faults | 851 | 14% | 16% | 30 a day, more than 3 of the other 4 years | 20 |
| Traincrew | 564 | 9% | 11% | 20 a day, the most in 5 years | 40 |
| Stations | 123 | 2% | 3% | 4 a day, the most in 5 years | 1 |
| Operations | 275 | 4% | 5% | 10 a day, the most in 5 years | 3 |
| Operator, other | 407 | 6% | 7% | 15 a day, more than 3 of the other 4 years | 1 |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IH | Power Supply And Distribution System Failure | 759 |
| JX | Miscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains) | 479 |
| OU | Delays not Investigated by Network Rail | 413 |
| TG | Driver | 399 |
| Q3 | NZ Pumps T | 367 |
| XO | External trees, building or structures encroaching or falling onto network infrastructure (not weather or vandalism) | 355 |
| TT | Leaf fall Neutral | 348 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 330 |
| M7 | Door and Door system faults | 273 |
| QJ | Special working for leaf-fall track circuit operation | 235 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| MD | Technical failures below the solebar | 10,160 |
| TG | Driver | 10,022 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 5,075 |
| M7 | Door and Door system faults | 4,882 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 4,400 |
| M8 | Technical failures above the Solebar | 4,190 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 4,113 |
| IV | Cutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure) | 4,010 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 3,781 |
| Q3 | NZ Pumps T | 3,676 |