Bridlington
2,103 delay minutes
The biggest share (16%) of the delay picked up at Bridlington in the four weeks to 9 December 2023 came from signal, points and power faults.
60% of these minutes were knock-on from something that happened elsewhere first. 95% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 169 | 8% | 8% | 6 a day, more than 3 of the other 4 years | - |
| Signals, points and power | 333 | 16% | 16% | 12 a day, more than 3 of the other 4 years | - |
| Weather and structures | 69 | 3% | 7% | 2 a day, more than 3 of the other 4 years | - |
| Autumn | 282 | 13% | 7% | 10 a day, more than 2 of the other 4 years | 1 |
| External | 65 | 3% | 4% | 2 a day, the most in 5 years | - |
| Network management | 310 | 15% | 17% | 11 a day, the most in 5 years | 1 |
| The operators' causes | |||||
| Train faults | 306 | 15% | 16% | 11 a day, the most in 5 years | 9 |
| Traincrew | 187 | 9% | 11% | 7 a day, the most in 5 years | 18 |
| Stations | 158 | 8% | 3% | 6 a day, the most in 5 years | - |
| Operations | 73 | 3% | 5% | 3 a day, the most in 5 years | - |
| Operator, other | 152 | 7% | 7% | 5 a day, more than 1 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| MD | Technical failures below the solebar | 189 |
| OU | Delays not Investigated by Network Rail | 166 |
| TG | Driver | 162 |
| Q3 | NZ Pumps T | 152 |
| TT | Leaf fall Neutral | 150 |
| ID | Level crossing faults and failure incl. barrow/foot crossings and crossing treadles | 140 |
| JS | Condition of Track TSR outside the Timetable Planning Rules | 125 |
| OE | Failure to lay Sandite or operate Railhead Conditioning train as programmed | 76 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 65 |
| XN | Road or crossing related incidents inc. cars on line, crossing misuse and priority to emergency services (NOT bridge strikes) | 60 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| MD | Technical failures below the solebar | 3,539 |
| JS | Condition of Track TSR outside the Timetable Planning Rules | 3,459 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 2,906 |
| IC | Track circuit failure (including no fault found) | 2,610 |
| Q3 | NZ Pumps T | 2,456 |
| RC | re-booked assistance for a person with reduced mobility joining/alighting, | 2,136 |
| TT | Leaf fall Neutral | 2,030 |
| RB | Passengers joining/alighting | 1,857 |
| TG | Driver | 1,824 |
| OU | Delays not Investigated by Network Rail | 1,569 |