Bethnal Green
880 delay minutes
The biggest share (36%) of the delay picked up at Bethnal Green in the four weeks to 9 December 2023 came from how the network was run.
83% of these minutes were knock-on from something that happened elsewhere first. 93% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 59 | 7% | 8% | 2 a day, the least in 5 years | - |
| Signals, points and power | 142 | 16% | 16% | 5 a day, the least in 5 years | - |
| Weather and structures | 50 | 6% | 7% | 2 a day, more than 2 of the other 4 years | - |
| Autumn | - | - | 7% | 0 a day, the least in 5 years | - |
| External | 82 | 9% | 4% | 3 a day, the most in 5 years | - |
| Network management | 316 | 36% | 17% | 11 a day, more than 2 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 72 | 8% | 16% | 3 a day, the least in 5 years | - |
| Traincrew | 33 | 4% | 11% | 1 a day, more than 1 of the other 4 years | - |
| Stations | 9 | 1% | 3% | 0 a day, the least in 5 years | - |
| Operations | 60 | 7% | 5% | 2 a day, more than 2 of the other 4 years | - |
| Operator, other | 58 | 7% | 7% | 2 a day, more than 2 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| I8 | Animal Strike or Incursion within the control of Network Rail | 127 |
| XP | BRIDGE HIT | 82 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 59 |
| IC | Track circuit failure (including no fault found) | 57 |
| I2 | AC/DC trip (including no fault or cause found) | 51 |
| OH | ARS / TMS / SARS software problem (excluding scheduling issues and technical failures) | 51 |
| IV | Cutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure) | 50 |
| J9 | Preventative Maintenance to the infrastructure in response to a Remote Condition Monitoring Alert | 49 |
| VH | Passenger Communication cord, door egress or emergency train alarm operated | 41 |
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 34 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 9,292 |
| IB | Points failure (including no fault found) | 5,669 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 4,631 |
| TG | Driver | 4,586 |
| MD | Technical failures below the solebar | 4,201 |
| M8 | Technical failures above the Solebar | 3,711 |
| M7 | Door and Door system faults | 3,364 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 2,781 |
| IC | Track circuit failure (including no fault found) | 2,683 |
| JL | Safety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff) | 2,378 |