440 delay minutes
The biggest share (47%) of the delay picked up at Bellingham in the four weeks to 9 December 2023 came from how the network was run.
83% of these minutes were knock-on from something that happened elsewhere first. 98% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 4 | <1% | 8% | 0 a day, more than 1 of the other 4 years | - |
| Signals, points and power | 43 | 10% | 16% | 2 a day, the least in 5 years | - |
| Weather and structures | 11 | 3% | 7% | 0 a day, more than 3 of the other 4 years | - |
| Autumn | 38 | 9% | 7% | 1 a day, more than 1 of the other 4 years | - |
| External | 3 | <1% | 4% | 0 a day, the least in 5 years | - |
| Network management | 208 | 47% | 17% | 7 a day, the most in 5 years | - |
| The operators' causes | |||||
| Train faults | 14 | 3% | 16% | 1 a day, more than 1 of the other 4 years | 1 |
| Traincrew | 28 | 6% | 11% | 1 a day, more than 2 of the other 4 years | - |
| Stations | 19 | 4% | 3% | 1 a day, more than 3 of the other 4 years | - |
| Operations | 3 | <1% | 5% | 0 a day, more than 1 of the other 4 years | - |
| Operator, other | 70 | 16% | 7% | 2 a day, the least in 5 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 159 |
| Q3 | NZ Pumps T | 38 |
| TT | Leaf fall Neutral | 36 |
| VH | Passenger Communication cord, door egress or emergency train alarm operated | 32 |
| TG | Driver | 28 |
| IC | Track circuit failure (including no fault found) | 16 |
| I6 | Delays as a result of line blocks / track patrols (including late handback) | 15 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 14 |
| IB | Points failure (including no fault found) | 9 |
| JD | Structures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes) | 8 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 5,092 |
| TG | Driver | 1,782 |
| VH | Passenger Communication cord, door egress or emergency train alarm operated | 1,743 |
| IC | Track circuit failure (including no fault found) | 1,307 |
| IB | Points failure (including no fault found) | 1,194 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 754 |
| M8 | Technical failures above the Solebar | 724 |
| TT | Leaf fall Neutral | 704 |
| XP | BRIDGE HIT | 667 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 638 |