Leaves on the Line

Barrow-in-Furness

BIF North West route
CSV JSON

2,348 delay minutes

The biggest share (34%) of the delay picked up at Barrow-in-Furness in the four weeks to 9 December 2023 came from weather and structures.

33% of these minutes were knock-on from something that happened elsewhere first. 94% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track13<1%8% 0 a day, more than 1 of the other 4 years-
Signals, points and power23810%16% 9 a day, more than 3 of the other 4 years4
Weather and structures79834%7% 29 a day, the most in 5 years15
Autumn432%7% 2 a day, more than 3 of the other 4 years-
External301%4% 1 a day, more than 1 of the other 4 years-
Network management40917%17% 15 a day, the most in 5 years60
The operators' causes
Train faults2008%16% 7 a day, the least in 5 years1
Traincrew37416%11% 13 a day, the most in 5 years73
Stations23<1%3% 1 a day, more than 1 of the other 4 years-
Operations1717%5% 6 a day, more than 3 of the other 4 years3
Operator, other512%7% 2 a day, more than 3 of the other 4 years2

Period by period

Delay minutes a day, period by period. Gridlines every 20 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
XTSevere snow or ice affecting infrastructure which is the responsibility of NR (including implementation of Key Route Strategy)547
TGDriver282
X9Points failure caused by severe snow or ice where heaters are fitted and working as designed222
IBPoints failure (including no fault found)125
JXMiscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains)106
OUDelays not Investigated by Network Rail100
JPFailure to maintain vegetation within network boundaries in accordance with prevailing Network Rail standards85
TH(Senior) Conductor/Train Manager62
TRTrain Operating Company Directive58
JLSafety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff)55
Since 2018
CodeWhat Network Rail loggedMinutes
TGDriver7,627
MDTechnical failures below the solebar3,983
TH(Senior) Conductor/Train Manager2,372
RBPassengers joining/alighting1,587
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)1,578
M7Door and Door system faults1,561
M8Technical failures above the Solebar1,528
MSPlanned underpowered or shortformed service and or vehicle, incl. exam set swaps1,514
IASignal failure (including no fault found)1,435
IBPoints failure (including no fault found)1,251