Bingham
1,588 delay minutes
Most of the delay picked up at Bingham in the four weeks to 9 December 2023 came from autumn leaves.
44% of these minutes were knock-on from something that happened elsewhere first. 93% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 17 | 1% | 8% | 1 a day, more than 1 of the other 4 years | - |
| Signals, points and power | 168 | 11% | 16% | 6 a day, more than 3 of the other 4 years | - |
| Weather and structures | 45 | 3% | 7% | 2 a day, the most in 5 years | - |
| Autumn | 818 | 51% | 7% | 29 a day, the most in 5 years | - |
| External | 13 | <1% | 4% | 0 a day, more than 1 of the other 4 years | - |
| Network management | 166 | 10% | 17% | 6 a day, more than 3 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 165 | 10% | 16% | 6 a day, more than 3 of the other 4 years | - |
| Traincrew | 38 | 2% | 11% | 1 a day, more than 1 of the other 4 years | - |
| Stations | 40 | 3% | 3% | 1 a day, more than 3 of the other 4 years | - |
| Operations | 8 | <1% | 5% | 0 a day, the least in 5 years | - |
| Operator, other | 111 | 7% | 7% | 4 a day, the most in 5 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| QJ | Special working for leaf-fall track circuit operation | 683 |
| Q3 | NZ Pumps T | 102 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 86 |
| OU | Delays not Investigated by Network Rail | 76 |
| M8 | Technical failures above the Solebar | 51 |
| MD | Technical failures below the solebar | 50 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 40 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 29 |
| II | Signalling lineside cable fault | 28 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 28 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| MD | Technical failures below the solebar | 2,019 |
| TG | Driver | 1,851 |
| M8 | Technical failures above the Solebar | 1,238 |
| ID | Level crossing faults and failure incl. barrow/foot crossings and crossing treadles | 1,133 |
| J3 | Axle Counter Failure | 1,031 |
| Q1 | Takeback Pumps | 994 |
| QJ | Special working for leaf-fall track circuit operation | 991 |
| M7 | Door and Door system faults | 751 |
| IC | Track circuit failure (including no fault found) | 722 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 705 |