Beckenham Junction
2,548 delay minutes
The biggest share (27%) of the delay picked up at Beckenham Junction in the four weeks to 9 December 2023 came from other operator causes.
85% of these minutes were knock-on from something that happened elsewhere first. 99% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 47 | 2% | 8% | 2 a day, more than 1 of the other 4 years | - |
| Signals, points and power | 139 | 5% | 16% | 5 a day, more than 1 of the other 4 years | 5 |
| Weather and structures | 20 | <1% | 7% | 1 a day, more than 1 of the other 4 years | - |
| Autumn | 646 | 25% | 7% | 23 a day, the most in 5 years | - |
| External | 22 | <1% | 4% | 1 a day, the least in 5 years | - |
| Network management | 582 | 23% | 17% | 21 a day, more than 3 of the other 4 years | 8 |
| The operators' causes | |||||
| Train faults | 223 | 9% | 16% | 8 a day, more than 2 of the other 4 years | 4 |
| Traincrew | 109 | 4% | 11% | 4 a day, more than 2 of the other 4 years | 2 |
| Stations | 29 | 1% | 3% | 1 a day, more than 1 of the other 4 years | - |
| Operations | 55 | 2% | 5% | 2 a day, the most in 5 years | - |
| Operator, other | 677 | 27% | 7% | 24 a day, more than 3 of the other 4 years | 1 |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| Q3 | NZ Pumps T | 578 |
| TT | Leaf fall Neutral | 567 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 281 |
| VH | Passenger Communication cord, door egress or emergency train alarm operated | 86 |
| TG | Driver | 75 |
| QH | Adhesion problems due to leaf contamination | 63 |
| IC | Track circuit failure (including no fault found) | 58 |
| I5 | Possession over-run from planned work | 55 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 51 |
| OS | Late start or delays to Railhead Conditioning or Ghost Train due to its own activity and not in reaction to another incident | 49 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 18,727 |
| TG | Driver | 5,136 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 4,136 |
| IC | Track circuit failure (including no fault found) | 4,023 |
| VH | Passenger Communication cord, door egress or emergency train alarm operated | 3,701 |
| TT | Leaf fall Neutral | 3,573 |
| IB | Points failure (including no fault found) | 3,003 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 2,570 |
| Q3 | NZ Pumps T | 2,518 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 2,209 |