Bournemouth
5,273 delay minutes
The biggest share (25%) of the delay picked up at Bournemouth in the four weeks to 9 December 2023 came from track faults.
76% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 1,329 | 25% | 8% | 47 a day, more than 3 of the other 4 years | 16 |
| Signals, points and power | 1,265 | 24% | 16% | 45 a day, the most in 5 years | 13 |
| Weather and structures | 173 | 3% | 7% | 6 a day, more than 2 of the other 4 years | 4 |
| Autumn | 208 | 4% | 7% | 7 a day, the most in 5 years | - |
| External | 58 | 1% | 4% | 2 a day, more than 1 of the other 4 years | - |
| Network management | 501 | 9% | 17% | 18 a day, more than 2 of the other 4 years | 27 |
| The operators' causes | |||||
| Train faults | 960 | 18% | 16% | 34 a day, the most in 5 years | 21 |
| Traincrew | 342 | 6% | 11% | 12 a day, the most in 5 years | 35 |
| Stations | 59 | 1% | 3% | 2 a day, more than 2 of the other 4 years | - |
| Operations | 181 | 3% | 5% | 6 a day, the most in 5 years | 14 |
| Operator, other | 198 | 4% | 7% | 7 a day, more than 3 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 1,116 |
| MD | Technical failures below the solebar | 729 |
| II | Signalling lineside cable fault | 617 |
| IB | Points failure (including no fault found) | 355 |
| TG | Driver | 273 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 193 |
| Q3 | NZ Pumps T | 176 |
| TT | Leaf fall Neutral | 176 |
| IE | Signalling Functional Power Supply Failure | 146 |
| TB | Train cancelled or delayed at Train Operators request | 128 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 18,914 |
| IC | Track circuit failure (including no fault found) | 6,670 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 5,118 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 5,036 |
| TG | Driver | 4,695 |
| MD | Technical failures below the solebar | 4,524 |
| IB | Points failure (including no fault found) | 3,961 |
| II | Signalling lineside cable fault | 3,086 |
| TH | (Senior) Conductor/Train Manager | 2,804 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 2,668 |