Leaves on the Line

Birmingham Moor Street

BMO Central route
CSV JSON

982 delay minutes

The biggest share (30%) of the delay picked up at Birmingham Moor Street in the four weeks to 9 December 2023 came from faulty trains.

67% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track101%8% 0 a day, the least in 5 years-
Signals, points and power21822%16% 8 a day, more than 3 of the other 4 years-
Weather and structures--7% 0 a day, the least in 5 years-
Autumn525%7% 2 a day, the most in 5 years-
External384%4% 1 a day, the most in 5 years1
Network management818%17% 3 a day, the least in 5 years2
The operators' causes
Train faults29530%16% 11 a day, more than 3 of the other 4 years6
Traincrew17318%11% 6 a day, more than 2 of the other 4 years6
Stations495%3% 2 a day, more than 2 of the other 4 years-
Operations162%5% 1 a day, more than 2 of the other 4 years2
Operator, other515%7% 2 a day, more than 2 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 20 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
TGDriver141
MDTechnical failures below the solebar134
IBPoints failure (including no fault found)122
M8Technical failures above the Solebar65
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure48
XPBRIDGE HIT36
MUDepot operating problem27
OCSignaller including mis-routing (not ERTM /ETCS related)25
QJSpecial working for leaf-fall track circuit operation22
IISignalling lineside cable fault21
Since 2018
CodeWhat Network Rail loggedMinutes
JSCondition of Track TSR outside the Timetable Planning Rules6,853
TGDriver6,039
MDTechnical failures below the solebar3,341
IBPoints failure (including no fault found)1,920
ICTrack circuit failure (including no fault found)1,804
TH(Senior) Conductor/Train Manager1,754
M8Technical failures above the Solebar1,661
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)1,535
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.1,429
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure1,379