Burnley Central
64 delay minutes
Most of the delay picked up at Burnley Central in the four weeks to 9 December 2023 came from outside causes like vandalism, cable theft, animals and fires.
89% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | Trains cancelled |
|---|---|---|---|---|
| Network Rail's causes | ||||
| Track | - | - | 8% | - |
| Signals, points and power | - | - | 16% | - |
| Weather and structures | - | - | 7% | - |
| Autumn | - | - | 7% | - |
| External | 64 | 100% | 4% | 1 |
| Network management | - | - | 17% | - |
| The operators' causes | ||||
| Train faults | - | - | 16% | - |
| Traincrew | - | - | 11% | 1 |
| Stations | - | - | 3% | - |
| Operations | - | - | 5% | - |
| Operator, other | - | - | 7% | - |
Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| XK | National Grid Power Failure - local area also affected (inc outage, surges, blips where working standby generator/UPS installed) | 64 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| XK | National Grid Power Failure - local area also affected (inc outage, surges, blips where working standby generator/UPS installed) | 64 |
| IC | Track circuit failure (including no fault found) | 58 |
| TG | Driver | 50 |
| MD | Technical failures below the solebar | 49 |
| T3 | Waiting connections from other transport modes | 41 |
| QH | Adhesion problems due to leaf contamination | 40 |
| XP | BRIDGE HIT | 39 |
| VZ | Other passenger or external causes the responsibility of TOC | 32 |
| M0 | Confirmed train cab based safety system fault (including GSMR) | 30 |
| Q3 | NZ Pumps T | 29 |