Leaves on the Line

Barnstaple

BNP Western route
CSV JSON

971 delay minutes

The biggest share (30%) of the delay picked up at Barnstaple in the four weeks to 9 December 2023 came from autumn leaves.

86% of these minutes were knock-on from something that happened elsewhere first. 98% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track6<1%8% 0 a day, more than 1 of the other 4 years-
Signals, points and power21522%16% 8 a day, the most in 5 years-
Weather and structures4<1%7% 0 a day, more than 1 of the other 4 years-
Autumn29230%7% 10 a day, the most in 5 years1
External4<1%4% 0 a day, more than 1 of the other 4 years-
Network management11912%17% 4 a day, more than 3 of the other 4 years-
The operators' causes
Train faults18819%16% 7 a day, more than 3 of the other 4 years2
Traincrew283%11% 1 a day, more than 3 of the other 4 years1
Stations8<1%3% 0 a day, more than 1 of the other 4 years-
Operations8<1%5% 0 a day, the most in 5 years-
Operator, other10010%7% 4 a day, more than 3 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 20 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
QICautioning due to railhead leaf contamination192
ICTrack circuit failure (including no fault found)113
Q3NZ Pumps T100
TTLeaf fall Neutral100
MRSanders and scrubber faults87
MDTechnical failures below the solebar72
I8Animal Strike or Incursion within the control of Network Rail65
IBPoints failure (including no fault found)36
OUDelays not Investigated by Network Rail35
MSPlanned underpowered or shortformed service and or vehicle, incl. exam set swaps23
Since 2018
CodeWhat Network Rail loggedMinutes
JSCondition of Track TSR outside the Timetable Planning Rules2,437
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.2,102
MDTechnical failures below the solebar2,100
JHCritical Rail Temperature speeds, (other than buckled rails)1,848
IBPoints failure (including no fault found)1,193
TGDriver1,166
M7Door and Door system faults1,053
ITRough ride or bumps reported - cause not known or no fault found930
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail913
M8Technical failures above the Solebar903