Barnes
792 delay minutes
The biggest share (39%) of the delay picked up at Barnes in the four weeks to 9 December 2023 came from how the network was run.
62% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 12 | 2% | 8% | 0 a day, more than 1 of the other 4 years | - |
| Signals, points and power | 62 | 8% | 16% | 2 a day, more than 1 of the other 4 years | - |
| Weather and structures | 3 | <1% | 7% | 0 a day, the least in 5 years | - |
| Autumn | 66 | 8% | 7% | 2 a day, more than 2 of the other 4 years | - |
| External | - | - | 4% | 0 a day, the least in 5 years | - |
| Network management | 308 | 39% | 17% | 11 a day, more than 1 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 51 | 6% | 16% | 2 a day, the least in 5 years | - |
| Traincrew | 99 | 13% | 11% | 4 a day, more than 1 of the other 4 years | - |
| Stations | 88 | 11% | 3% | 3 a day, more than 2 of the other 4 years | - |
| Operations | 22 | 3% | 5% | 1 a day, more than 3 of the other 4 years | - |
| Operator, other | 81 | 10% | 7% | 3 a day, the least in 5 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 115 |
| T2 | Delay at unstaffed station to non-DOO train | 78 |
| I6 | Delays as a result of line blocks / track patrols (including late handback) | 71 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 70 |
| TG | Driver | 66 |
| Q3 | NZ Pumps T | 43 |
| TT | Leaf fall Neutral | 43 |
| VH | Passenger Communication cord, door egress or emergency train alarm operated | 24 |
| OE | Failure to lay Sandite or operate Railhead Conditioning train as programmed | 23 |
| IC | Track circuit failure (including no fault found) | 21 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 6,506 |
| JD | Structures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes) | 4,056 |
| I1 | Overhead line/third rail defect | 3,122 |
| TG | Driver | 3,063 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 2,746 |
| IC | Track circuit failure (including no fault found) | 2,623 |
| I6 | Delays as a result of line blocks / track patrols (including late handback) | 2,464 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 2,264 |
| VH | Passenger Communication cord, door egress or emergency train alarm operated | 2,225 |
| T2 | Delay at unstaffed station to non-DOO train | 2,076 |