15 delay minutes

The biggest share (40%) of the delay picked up at Broadstairs in the four weeks to 9 December 2023 came from faulty trains.

80% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power--16%-
Weather and structures--7%-
Autumn--7%-
External--4%-
Network management427%17%-
The operators' causes
Train faults640%16%-
Traincrew533%11%-
Stations--3%-
Operations--5%-
Operator, other--7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 1 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
TITraincrew rostering problem5
MNBrake and brake systems faults; including wheel flats where no other cause had been identified3
MUDepot operating problem3
QAWTT schedule and or LTP Process including erroneous simplifiers3
OCSignaller including mis-routing (not ERTM /ETCS related)1
Since 2018
CodeWhat Network Rail loggedMinutes
TZOther Passenger Train Operating Company causes198
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)85
IHPower Supply And Distribution System Failure80
TGDriver79
OCSignaller including mis-routing (not ERTM /ETCS related)58
M0Confirmed train cab based safety system fault (including GSMR)54
TITraincrew rostering problem53
VHPassenger Communication cord, door egress or emergency train alarm operated53
IISignalling lineside cable fault52
M8Technical failures above the Solebar40