1,354 delay minutes

The biggest share (31%) of the delay picked up at Birmingham Snow Hill in the four weeks to 9 December 2023 came from traincrew problems.

45% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track10<1%8% 0 a day, the least in 5 years-
Signals, points and power17713%16% 6 a day, more than 1 of the other 4 years12
Weather and structures343%7% 1 a day, more than 1 of the other 4 years-
Autumn574%7% 2 a day, more than 1 of the other 4 years-
External725%4% 3 a day, more than 3 of the other 4 years2
Network management695%17% 2 a day, the least in 5 years33
The operators' causes
Train faults39229%16% 14 a day, the most in 5 years15
Traincrew41931%11% 15 a day, more than 1 of the other 4 years79
Stations201%3% 1 a day, the least in 5 years-
Operations13<1%5% 0 a day, more than 2 of the other 4 years2
Operator, other917%7% 3 a day, more than 1 of the other 4 years1

Period by period

Delay minutes a day, period by period. Gridlines every 50 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
TGDriver372
M8Technical failures above the Solebar247
IBPoints failure (including no fault found)142
MPRail / wheel interface, adhesion problems (including ice on the running rail)61
XPBRIDGE HIT58
MDTechnical failures below the solebar52
M0Confirmed train cab based safety system fault (including GSMR)44
JKFlooding not due to exceptional weather34
M7Door and Door system faults33
TH(Senior) Conductor/Train Manager32
Since 2018
CodeWhat Network Rail loggedMinutes
TGDriver14,327
MDTechnical failures below the solebar6,499
TH(Senior) Conductor/Train Manager4,442
M8Technical failures above the Solebar4,244
ZUNo Cause Identified After investigation by both Parties3,605
IASignal failure (including no fault found)2,892
ICTrack circuit failure (including no fault found)2,888
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)2,264
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure2,213
IBPoints failure (including no fault found)2,112