Birmingham Snow Hill
1,354 delay minutes
The biggest share (31%) of the delay picked up at Birmingham Snow Hill in the four weeks to 9 December 2023 came from traincrew problems.
45% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 10 | <1% | 8% | 0 a day, the least in 5 years | - |
| Signals, points and power | 177 | 13% | 16% | 6 a day, more than 1 of the other 4 years | 12 |
| Weather and structures | 34 | 3% | 7% | 1 a day, more than 1 of the other 4 years | - |
| Autumn | 57 | 4% | 7% | 2 a day, more than 1 of the other 4 years | - |
| External | 72 | 5% | 4% | 3 a day, more than 3 of the other 4 years | 2 |
| Network management | 69 | 5% | 17% | 2 a day, the least in 5 years | 33 |
| The operators' causes | |||||
| Train faults | 392 | 29% | 16% | 14 a day, the most in 5 years | 15 |
| Traincrew | 419 | 31% | 11% | 15 a day, more than 1 of the other 4 years | 79 |
| Stations | 20 | 1% | 3% | 1 a day, the least in 5 years | - |
| Operations | 13 | <1% | 5% | 0 a day, more than 2 of the other 4 years | 2 |
| Operator, other | 91 | 7% | 7% | 3 a day, more than 1 of the other 4 years | 1 |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 372 |
| M8 | Technical failures above the Solebar | 247 |
| IB | Points failure (including no fault found) | 142 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 61 |
| XP | BRIDGE HIT | 58 |
| MD | Technical failures below the solebar | 52 |
| M0 | Confirmed train cab based safety system fault (including GSMR) | 44 |
| JK | Flooding not due to exceptional weather | 34 |
| M7 | Door and Door system faults | 33 |
| TH | (Senior) Conductor/Train Manager | 32 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 14,327 |
| MD | Technical failures below the solebar | 6,499 |
| TH | (Senior) Conductor/Train Manager | 4,442 |
| M8 | Technical failures above the Solebar | 4,244 |
| ZU | No Cause Identified After investigation by both Parties | 3,605 |
| IA | Signal failure (including no fault found) | 2,892 |
| IC | Track circuit failure (including no fault found) | 2,888 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 2,264 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 2,213 |
| IB | Points failure (including no fault found) | 2,112 |