Brough
1,485 delay minutes
The biggest share (22%) of the delay picked up at Brough in the four weeks to 9 December 2023 came from faulty trains.
53% of these minutes were knock-on from something that happened elsewhere first. 95% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 42 | 3% | 8% | 2 a day, more than 3 of the other 4 years | - |
| Signals, points and power | 236 | 16% | 16% | 8 a day, the least in 5 years | - |
| Weather and structures | 68 | 5% | 7% | 2 a day, more than 2 of the other 4 years | - |
| Autumn | 129 | 9% | 7% | 5 a day, more than 3 of the other 4 years | - |
| External | 91 | 6% | 4% | 3 a day, the most in 5 years | - |
| Network management | 293 | 20% | 17% | 10 a day, more than 3 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 332 | 22% | 16% | 12 a day, the most in 5 years | - |
| Traincrew | 102 | 7% | 11% | 4 a day, the most in 5 years | - |
| Stations | 53 | 4% | 3% | 2 a day, the most in 5 years | - |
| Operations | 84 | 6% | 5% | 3 a day, the most in 5 years | - |
| Operator, other | 56 | 4% | 7% | 2 a day, more than 3 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 182 |
| OU | Delays not Investigated by Network Rail | 179 |
| IC | Track circuit failure (including no fault found) | 88 |
| TG | Driver | 78 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 70 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 61 |
| QJ | Special working for leaf-fall track circuit operation | 60 |
| MU | Depot operating problem | 56 |
| Q3 | NZ Pumps T | 53 |
| TT | Leaf fall Neutral | 53 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 5,306 |
| ID | Level crossing faults and failure incl. barrow/foot crossings and crossing treadles | 4,719 |
| JS | Condition of Track TSR outside the Timetable Planning Rules | 2,815 |
| TG | Driver | 2,355 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 2,266 |
| MD | Technical failures below the solebar | 1,982 |
| J3 | Axle Counter Failure | 1,680 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 1,469 |
| XN | Road or crossing related incidents inc. cars on line, crossing misuse and priority to emergency services (NOT bridge strikes) | 1,222 |
| II | Signalling lineside cable fault | 1,019 |