Leaves on the Line

Brough

BUH North & East route
CSV JSON

1,485 delay minutes

The biggest share (22%) of the delay picked up at Brough in the four weeks to 9 December 2023 came from faulty trains.

53% of these minutes were knock-on from something that happened elsewhere first. 95% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track423%8% 2 a day, more than 3 of the other 4 years-
Signals, points and power23616%16% 8 a day, the least in 5 years-
Weather and structures685%7% 2 a day, more than 2 of the other 4 years-
Autumn1299%7% 5 a day, more than 3 of the other 4 years-
External916%4% 3 a day, the most in 5 years-
Network management29320%17% 10 a day, more than 3 of the other 4 years-
The operators' causes
Train faults33222%16% 12 a day, the most in 5 years-
Traincrew1027%11% 4 a day, the most in 5 years-
Stations534%3% 2 a day, the most in 5 years-
Operations846%5% 3 a day, the most in 5 years-
Operator, other564%7% 2 a day, more than 3 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 20 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
MNBrake and brake systems faults; including wheel flats where no other cause had been identified182
OUDelays not Investigated by Network Rail179
ICTrack circuit failure (including no fault found)88
TGDriver78
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure70
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail61
QJSpecial working for leaf-fall track circuit operation60
MUDepot operating problem56
Q3NZ Pumps T53
TTLeaf fall Neutral53
Since 2018
CodeWhat Network Rail loggedMinutes
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.5,306
IDLevel crossing faults and failure incl. barrow/foot crossings and crossing treadles4,719
JSCondition of Track TSR outside the Timetable Planning Rules2,815
TGDriver2,355
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure2,266
MDTechnical failures below the solebar1,982
J3Axle Counter Failure1,680
OCSignaller including mis-routing (not ERTM /ETCS related)1,469
XNRoad or crossing related incidents inc. cars on line, crossing misuse and priority to emergency services (NOT bridge strikes)1,222
IISignalling lineside cable fault1,019