Leaves on the Line

Buxton

BUX North West route
CSV JSON

785 delay minutes

The biggest share (41%) of the delay picked up at Buxton in the four weeks to 9 December 2023 came from how the network was run.

50% of these minutes were knock-on from something that happened elsewhere first. 91% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track--8% 0 a day, the least in 5 years-
Signals, points and power19325%16% 7 a day, the most in 5 years-
Weather and structures334%7% 1 a day, more than 3 of the other 4 years1
Autumn162%7% 1 a day, more than 1 of the other 4 years2
External--4% 0 a day, the least in 5 years-
Network management32341%17% 12 a day, the most in 5 years6
The operators' causes
Train faults415%16% 1 a day, the least in 5 years4
Traincrew12516%11% 4 a day, more than 3 of the other 4 years6
Stations3<1%3% 0 a day, more than 1 of the other 4 years-
Operations446%5% 2 a day, more than 2 of the other 4 years-
Operator, other7<1%7% 0 a day, the least in 5 years-

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
OMTechnical failure associated with a Railhead conditioning train220
TGDriver119
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure80
OCSignaller including mis-routing (not ERTM /ETCS related)70
IASignal failure (including no fault found)49
IGBlock failure44
JKFlooding not due to exceptional weather33
MYCoupler, Coupler system and Jumper cable faults33
OUDelays not Investigated by Network Rail21
J0Telecom equipment radio failure (GSM-R)17
Since 2018
CodeWhat Network Rail loggedMinutes
TGDriver2,596
MDTechnical failures below the solebar1,930
IASignal failure (including no fault found)950
MNBrake and brake systems faults; including wheel flats where no other cause had been identified792
IBPoints failure (including no fault found)776
OLSignal Box not open during booked hours738
TH(Senior) Conductor/Train Manager731
QAWTT schedule and or LTP Process including erroneous simplifiers564
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)525
T8Delays at Station believed to be operator cause and Information required from operator (Ops responsibility)471