Leaves on the Line

Burnley Manchester Road

BYM North West route
CSV JSON

0 delay minutes

No delay was picked up at Burnley Manchester Road in the four weeks to 9 December 2023.

100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power--16%-
Weather and structures--7%-
Autumn--7%-
External--4%-
Network management--17%1
The operators' causes
Train faults--16%-
Traincrew--11%-
Stations--3%-
Operations--5%-
Operator, other--7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 2 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
Nothing logged.
Since 2018
CodeWhat Network Rail loggedMinutes
TGDriver81
XPBRIDGE HIT61
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.60
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure56
MUDepot operating problem53
MDTechnical failures below the solebar48
M8Technical failures above the Solebar47
Q3NZ Pumps T47
TTLeaf fall Neutral47
JDStructures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes)46