Carlisle
3,681 delay minutes
The biggest share (37%) of the delay picked up at Carlisle in the four weeks to 9 December 2023 came from faulty trains.
49% of these minutes were knock-on from something that happened elsewhere first. 86% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 9 | <1% | 8% | 0 a day, the least in 5 years | - |
| Signals, points and power | 263 | 7% | 16% | 9 a day, the least in 5 years | - |
| Weather and structures | 824 | 22% | 7% | 29 a day, the most in 5 years | 10 |
| Autumn | 55 | 1% | 7% | 2 a day, more than 2 of the other 4 years | - |
| External | 60 | 2% | 4% | 2 a day, more than 3 of the other 4 years | - |
| Network management | 500 | 14% | 17% | 18 a day, the most in 5 years | 73 |
| The operators' causes | |||||
| Train faults | 1,351 | 37% | 16% | 48 a day, the most in 5 years | 24 |
| Traincrew | 333 | 9% | 11% | 12 a day, more than 2 of the other 4 years | 28 |
| Stations | 110 | 3% | 3% | 4 a day, the most in 5 years | - |
| Operations | 73 | 2% | 5% | 3 a day, the least in 5 years | 3 |
| Operator, other | 105 | 3% | 7% | 4 a day, more than 2 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 539 |
| M1 | Confirmed Pantograph ADD, associated system faults, positive PANCHEX activations and train borne power switch over systems (AC) | 358 |
| MB | Electic Loco failure, defect, attention | 243 |
| TG | Driver | 202 |
| M8 | Technical failures above the Solebar | 170 |
| OU | Delays not Investigated by Network Rail | 157 |
| IB | Points failure (including no fault found) | 148 |
| XT | Severe snow or ice affecting infrastructure which is the responsibility of NR (including implementation of Key Route Strategy) | 137 |
| MD | Technical failures below the solebar | 126 |
| JL | Safety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff) | 109 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 12,600 |
| MD | Technical failures below the solebar | 7,478 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 6,063 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 5,659 |
| IB | Points failure (including no fault found) | 5,251 |
| M8 | Technical failures above the Solebar | 5,164 |
| MC | Diesel Loco failure, defect, attention | 4,046 |
| I1 | Overhead line/third rail defect | 3,741 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 3,636 |
| MB | Electic Loco failure, defect, attention | 3,344 |