Leaves on the Line

Canterbury East

CBE Kent route
CSV JSON

1,211 delay minutes

The biggest share (36%) of the delay picked up at Canterbury East in the four weeks to 9 December 2023 came from autumn leaves.

27% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track--8% 0 a day, the least in 5 years-
Signals, points and power716%16% 3 a day, more than 3 of the other 4 years-
Weather and structures16514%7% 6 a day, more than 2 of the other 4 years1
Autumn43436%7% 16 a day, the most in 5 years-
External--4% 0 a day, the least in 5 years-
Network management544%17% 2 a day, more than 1 of the other 4 years2
The operators' causes
Train faults252%16% 1 a day, more than 3 of the other 4 years-
Traincrew9<1%11% 0 a day, more than 2 of the other 4 years-
Stations6<1%3% 0 a day, more than 2 of the other 4 years-
Operations192%5% 1 a day, more than 3 of the other 4 years-
Operator, other42835%7% 15 a day, the most in 5 years-

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
Q3NZ Pumps T418
TTLeaf fall Neutral399
OGIce on conductor rail/OHLE165
ICTrack circuit failure (including no fault found)57
MPRail / wheel interface, adhesion problems (including ice on the running rail)20
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)19
QHAdhesion problems due to leaf contamination16
MSPlanned underpowered or shortformed service and or vehicle, incl. exam set swaps15
I1Overhead line/third rail defect14
OCSignaller including mis-routing (not ERTM /ETCS related)13
Since 2018
CodeWhat Network Rail loggedMinutes
JDStructures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes)7,936
IVCutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure)2,778
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)1,986
Q3NZ Pumps T1,901
TTLeaf fall Neutral1,769
MPRail / wheel interface, adhesion problems (including ice on the running rail)1,250
JPFailure to maintain vegetation within network boundaries in accordance with prevailing Network Rail standards1,007
TGDriver919
OCSignaller including mis-routing (not ERTM /ETCS related)694
JBReactionary Delay to 'P' coded TSRs677