Church Fenton
1,094 delay minutes
The biggest share (25%) of the delay picked up at Church Fenton in the four weeks to 9 December 2023 came from faulty trains.
85% of these minutes were knock-on from something that happened elsewhere first. 94% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 62 | 6% | 8% | 2 a day, more than 3 of the other 4 years | - |
| Signals, points and power | 88 | 8% | 16% | 3 a day, more than 2 of the other 4 years | - |
| Weather and structures | 88 | 8% | 7% | 3 a day, more than 3 of the other 4 years | - |
| Autumn | 89 | 8% | 7% | 3 a day, the most in 5 years | - |
| External | 61 | 6% | 4% | 2 a day, the most in 5 years | - |
| Network management | 214 | 20% | 17% | 8 a day, more than 3 of the other 4 years | 4 |
| The operators' causes | |||||
| Train faults | 270 | 25% | 16% | 10 a day, the most in 5 years | - |
| Traincrew | 115 | 11% | 11% | 4 a day, more than 3 of the other 4 years | - |
| Stations | 28 | 3% | 3% | 1 a day, more than 3 of the other 4 years | - |
| Operations | 40 | 4% | 5% | 1 a day, more than 3 of the other 4 years | - |
| Operator, other | 40 | 4% | 7% | 1 a day, more than 2 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 140 |
| OU | Delays not Investigated by Network Rail | 82 |
| QJ | Special working for leaf-fall track circuit operation | 57 |
| TG | Driver | 51 |
| TH | (Senior) Conductor/Train Manager | 50 |
| MD | Technical failures below the solebar | 49 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 43 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 42 |
| XO | External trees, building or structures encroaching or falling onto network infrastructure (not weather or vandalism) | 41 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 33 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| JA | TSR speed restrictions for track work outside of the Timetable Planning Rules | 2,809 |
| TG | Driver | 2,185 |
| MD | Technical failures below the solebar | 1,787 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 1,191 |
| M8 | Technical failures above the Solebar | 1,163 |
| IC | Track circuit failure (including no fault found) | 1,111 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 977 |
| TH | (Senior) Conductor/Train Manager | 962 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 955 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 944 |