Leaves on the Line

Cheshunt

CHN Anglia route
CSV JSON

828 delay minutes

The biggest share (27%) of the delay picked up at Cheshunt in the four weeks to 9 December 2023 came from how the network was run.

65% of these minutes were knock-on from something that happened elsewhere first. 91% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track243%8% 1 a day, the least in 5 years-
Signals, points and power9111%16% 3 a day, more than 2 of the other 4 years4
Weather and structures111%7% 0 a day, more than 3 of the other 4 years-
Autumn182%7% 1 a day, more than 2 of the other 4 years-
External15018%4% 5 a day, the most in 5 years4
Network management22327%17% 8 a day, the most in 5 years-
The operators' causes
Train faults10212%16% 4 a day, the least in 5 years3
Traincrew91%11% 0 a day, the least in 5 years3
Stations283%3% 1 a day, more than 2 of the other 4 years-
Operations638%5% 2 a day, the most in 5 years-
Operator, other11013%7% 4 a day, the most in 5 years-

Period by period

Delay minutes a day, period by period. Gridlines every 20 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
XPBRIDGE HIT133
VHPassenger Communication cord, door egress or emergency train alarm operated100
I2AC/DC trip (including no fault or cause found)88
JPFailure to maintain vegetation within network boundaries in accordance with prevailing Network Rail standards78
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)63
JXMiscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains)57
M0Confirmed train cab based safety system fault (including GSMR)31
OCSignaller including mis-routing (not ERTM /ETCS related)27
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.20
MNBrake and brake systems faults; including wheel flats where no other cause had been identified20
Since 2018
CodeWhat Network Rail loggedMinutes
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.4,088
TGDriver3,202
MDTechnical failures below the solebar3,015
M8Technical failures above the Solebar2,367
M7Door and Door system faults2,205
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure1,960
IBPoints failure (including no fault found)1,948
RBPassengers joining/alighting1,884
IRBroken/cracked/twisted/buckled/flawed rail1,708
XDLevel Crossing Incidents including misuse and emergency services being prioritised over rail services1,592