Clock House
19 delay minutes
Most of the delay picked up at Clock House in the four weeks to 9 December 2023 came from outside causes like vandalism, cable theft, animals and fires.
100% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | Trains cancelled |
|---|---|---|---|---|
| Network Rail's causes | ||||
| Track | - | - | 8% | - |
| Signals, points and power | - | - | 16% | - |
| Weather and structures | - | - | 7% | - |
| Autumn | - | - | 7% | - |
| External | 19 | 100% | 4% | - |
| Network management | - | - | 17% | - |
| The operators' causes | ||||
| Train faults | - | - | 16% | - |
| Traincrew | - | - | 11% | - |
| Stations | - | - | 3% | - |
| Operations | - | - | 5% | - |
| Operator, other | - | - | 7% | - |
Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| XP | BRIDGE HIT | 19 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IB | Points failure (including no fault found) | 272 |
| IC | Track circuit failure (including no fault found) | 269 |
| JP | Failure to maintain vegetation within network boundaries in accordance with prevailing Network Rail standards | 150 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 147 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 128 |
| I9 | Fires starting on Network Rail Infrastructure | 119 |
| IH | Power Supply And Distribution System Failure | 101 |
| MC | Diesel Loco failure, defect, attention | 92 |
| XP | BRIDGE HIT | 88 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 77 |