Leaves on the Line

Camden Road

CMD Anglia route
CSV JSON

395 delay minutes

The biggest share (18%) of the delay picked up at Camden Road in the four weeks to 9 December 2023 came from the operators' own operations.

90% of these minutes were knock-on from something that happened elsewhere first. 94% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track4211%8% 2 a day, more than 3 of the other 4 years8
Signals, points and power6115%16% 2 a day, more than 3 of the other 4 years3
Weather and structures123%7% 0 a day, more than 3 of the other 4 years3
Autumn--7% 0 a day, the least in 5 years-
External185%4% 1 a day, more than 3 of the other 4 years-
Network management4110%17% 1 a day, the least in 5 years7
The operators' causes
Train faults5614%16% 2 a day, more than 2 of the other 4 years3
Traincrew5313%11% 2 a day, more than 3 of the other 4 years-
Stations256%3% 1 a day, more than 2 of the other 4 years1
Operations7118%5% 3 a day, the most in 5 years3
Operator, other164%7% 1 a day, the least in 5 years-

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
IASignal failure (including no fault found)42
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)42
TGDriver41
M8Technical failures above the Solebar39
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.29
XOExternal trees, building or structures encroaching or falling onto network infrastructure (not weather or vandalism)15
RQUn-booked assistance for a person with reduced mobility joining/alighting,12
FXFreight train running at lower class or speed than planned classification or overweight11
AJWaiting Customer's traffic including release information and documentation10
IBPoints failure (including no fault found)10
Since 2018
CodeWhat Network Rail loggedMinutes
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.1,851
TGDriver1,739
J3Axle Counter Failure1,467
IBPoints failure (including no fault found)1,281
M8Technical failures above the Solebar973
MDTechnical failures below the solebar883
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail760
MCDiesel Loco failure, defect, attention757
VHPassenger Communication cord, door egress or emergency train alarm operated656
JXMiscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains)531