Leaves on the Line

Cromer

CMR Anglia route
CSV JSON

60 delay minutes

Most of the delay picked up at Cromer in the four weeks to 9 December 2023 came from signal, points and power faults.

37% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power3457%16%-
Weather and structures813%7%-
Autumn23%7%-
External--4%-
Network management--17%2
The operators' causes
Train faults--16%-
Traincrew--11%-
Stations--3%-
Operations--5%-
Operator, other1627%7%2

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
J0Telecom equipment radio failure (GSM-R)31
FWLate start/yard overtime not explained by Operator14
JKFlooding not due to exceptional weather8
IASignal failure (including no fault found)3
Q3NZ Pumps T2
TTLeaf fall Neutral2
MPRail / wheel interface, adhesion problems (including ice on the running rail)1
Since 2018
CodeWhat Network Rail loggedMinutes
Q1Takeback Pumps783
DDTechnical Fleet Holding Code731
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure592
MDTechnical failures below the solebar471
MUDepot operating problem417
M8Technical failures above the Solebar344
IASignal failure (including no fault found)258
J3Axle Counter Failure236
TGDriver219
M7Door and Door system faults200