Colne
796 delay minutes
The biggest share (38%) of the delay picked up at Colne in the four weeks to 9 December 2023 came from signal, points and power faults.
68% of these minutes were knock-on from something that happened elsewhere first. 91% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 26 | 3% | 8% | 1 a day, the most in 5 years | 1 |
| Signals, points and power | 299 | 38% | 16% | 11 a day, the most in 5 years | 2 |
| Weather and structures | 39 | 5% | 7% | 1 a day, more than 2 of the other 4 years | - |
| Autumn | 53 | 7% | 7% | 2 a day, the least in 5 years | - |
| External | 49 | 6% | 4% | 2 a day, more than 3 of the other 4 years | 2 |
| Network management | 101 | 13% | 17% | 4 a day, more than 1 of the other 4 years | 1 |
| The operators' causes | |||||
| Train faults | 123 | 15% | 16% | 4 a day, more than 1 of the other 4 years | - |
| Traincrew | 38 | 5% | 11% | 1 a day, the least in 5 years | 13 |
| Stations | 11 | 1% | 3% | 0 a day, the least in 5 years | - |
| Operations | 17 | 2% | 5% | 1 a day, the least in 5 years | - |
| Operator, other | 40 | 5% | 7% | 1 a day, the least in 5 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IB | Points failure (including no fault found) | 230 |
| OU | Delays not Investigated by Network Rail | 58 |
| M8 | Technical failures above the Solebar | 37 |
| MD | Technical failures below the solebar | 36 |
| Q3 | NZ Pumps T | 34 |
| IC | Track circuit failure (including no fault found) | 33 |
| TH | (Senior) Conductor/Train Manager | 33 |
| XB | Vandalism or theft (including the placing of objects on the line) | 28 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 25 |
| TT | Leaf fall Neutral | 24 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 2,529 |
| MD | Technical failures below the solebar | 2,426 |
| Q3 | NZ Pumps T | 2,132 |
| RC | re-booked assistance for a person with reduced mobility joining/alighting, | 2,126 |
| RB | Passengers joining/alighting | 1,940 |
| TT | Leaf fall Neutral | 1,592 |
| TR | Train Operating Company Directive | 1,047 |
| M7 | Door and Door system faults | 1,035 |
| TH | (Senior) Conductor/Train Manager | 966 |
| IB | Points failure (including no fault found) | 920 |