Leaves on the Line

Corby

COR East Midlands route
CSV JSON

343 delay minutes

The biggest share (28%) of the delay picked up at Corby in the four weeks to 9 December 2023 came from how the network was run.

78% of these minutes were knock-on from something that happened elsewhere first. 86% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track5416%8% 2 a day, the most in 5 years-
Signals, points and power206%16% 1 a day, more than 2 of the other 4 years-
Weather and structures154%7% 1 a day, more than 2 of the other 4 years1
Autumn92%7% 0 a day, more than 3 of the other 4 years-
External--4% 0 a day, the least in 5 years-
Network management9728%17% 3 a day, more than 3 of the other 4 years11
The operators' causes
Train faults4814%16% 2 a day, more than 2 of the other 4 years9
Traincrew7020%11% 3 a day, the most in 5 years9
Stations195%3% 1 a day, the most in 5 years-
Operations41%5% 0 a day, more than 1 of the other 4 years-
Operator, other92%7% 0 a day, more than 2 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
TGDriver47
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.37
I5Possession over-run from planned work34
JLSafety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff)31
IRBroken/cracked/twisted/buckled/flawed rail17
M8Technical failures above the Solebar17
Q1Takeback Pumps17
TITraincrew rostering problem15
M7Door and Door system faults14
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)11
Since 2018
CodeWhat Network Rail loggedMinutes
IVCutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure)1,728
JSCondition of Track TSR outside the Timetable Planning Rules1,343
M8Technical failures above the Solebar1,177
TGDriver884
M7Door and Door system faults638
MDTechnical failures below the solebar563
J3Axle Counter Failure466
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.403
MNBrake and brake systems faults; including wheel flats where no other cause had been identified397
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail368