Leaves on the Line

Chippenham

CPM Western route
CSV JSON

619 delay minutes

The biggest share (36%) of the delay picked up at Chippenham in the four weeks to 9 December 2023 came from track faults.

40% of these minutes were knock-on from something that happened elsewhere first. 97% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track22136%8% 8 a day, the most in 5 years-
Signals, points and power366%16% 1 a day, more than 2 of the other 4 years-
Weather and structures193%7% 1 a day, more than 2 of the other 4 years-
Autumn--7% 0 a day, the least in 5 years-
External--4% 0 a day, the least in 5 years-
Network management11318%17% 4 a day, more than 1 of the other 4 years-
The operators' causes
Train faults11819%16% 4 a day, more than 3 of the other 4 years-
Traincrew356%11% 1 a day, the most in 5 years-
Stations427%3% 2 a day, more than 3 of the other 4 years-
Operations254%5% 1 a day, the most in 5 years-
Operator, other112%7% 0 a day, the least in 5 years-

Period by period

Delay minutes a day, period by period. Gridlines every 20 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
IRBroken/cracked/twisted/buckled/flawed rail158
MVEngineers on-track equipment failure outside possession75
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.50
OCSignaller including mis-routing (not ERTM /ETCS related)28
OUDelays not Investigated by Network Rail27
JLSafety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff)26
IBPoints failure (including no fault found)22
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure19
TGDriver18
FOTime Lost en-route believed to be operator cause and information required from Operator (Ops Responsibility)15
Since 2018
CodeWhat Network Rail loggedMinutes
JSCondition of Track TSR outside the Timetable Planning Rules5,399
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.4,408
OCSignaller including mis-routing (not ERTM /ETCS related)1,567
J3Axle Counter Failure1,327
IBPoints failure (including no fault found)1,105
MDTechnical failures below the solebar956
QMTrain schedule/STP Process including erroneous simplifiers898
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure835
MCDiesel Loco failure, defect, attention747
AJWaiting Customer's traffic including release information and documentation727