Chippenham
619 delay minutes
The biggest share (36%) of the delay picked up at Chippenham in the four weeks to 9 December 2023 came from track faults.
40% of these minutes were knock-on from something that happened elsewhere first. 97% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 221 | 36% | 8% | 8 a day, the most in 5 years | - |
| Signals, points and power | 36 | 6% | 16% | 1 a day, more than 2 of the other 4 years | - |
| Weather and structures | 19 | 3% | 7% | 1 a day, more than 2 of the other 4 years | - |
| Autumn | - | - | 7% | 0 a day, the least in 5 years | - |
| External | - | - | 4% | 0 a day, the least in 5 years | - |
| Network management | 113 | 18% | 17% | 4 a day, more than 1 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 118 | 19% | 16% | 4 a day, more than 3 of the other 4 years | - |
| Traincrew | 35 | 6% | 11% | 1 a day, the most in 5 years | - |
| Stations | 42 | 7% | 3% | 2 a day, more than 3 of the other 4 years | - |
| Operations | 25 | 4% | 5% | 1 a day, the most in 5 years | - |
| Operator, other | 11 | 2% | 7% | 0 a day, the least in 5 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IR | Broken/cracked/twisted/buckled/flawed rail | 158 |
| MV | Engineers on-track equipment failure outside possession | 75 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 50 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 28 |
| OU | Delays not Investigated by Network Rail | 27 |
| JL | Safety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff) | 26 |
| IB | Points failure (including no fault found) | 22 |
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 19 |
| TG | Driver | 18 |
| FO | Time Lost en-route believed to be operator cause and information required from Operator (Ops Responsibility) | 15 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| JS | Condition of Track TSR outside the Timetable Planning Rules | 5,399 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 4,408 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 1,567 |
| J3 | Axle Counter Failure | 1,327 |
| IB | Points failure (including no fault found) | 1,105 |
| MD | Technical failures below the solebar | 956 |
| QM | Train schedule/STP Process including erroneous simplifiers | 898 |
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 835 |
| MC | Diesel Loco failure, defect, attention | 747 |
| AJ | Waiting Customer's traffic including release information and documentation | 727 |